DESIGN AND CONSTRUCTION OF THE DOME OF
THE MAHAWELI MAHASEYA (STUPA) AS A THIN SHELL ANALYSIS AND DESIGN
The Structure was analyzed by solving compatibility and equilibrium
equitation for the redundant forces occurring at edges where shell
and ring beam meet. The resultant bending forces were super-imposed
on the membrane forces to obtain the total stresses. The procedure
was repeated for various Loading cases and various Loading combinations.
The
structure was analyzed by analytic methods as well as by the finite.
Element method and the results were compared and found to be compatible.
The maximum values of the forces obtained under either method were
adopted in the final design. The dome was also checked for intermediate
construction stages.
DESIGN
AND CONSTRUCTION OF THE DOME OF THE MAHAWELI MAHASEYA (STUPA) AS
A THIN SHELL ANALYSIS AND DESIGN
The
following nine loads and loading conditions were considered for
the design analysis:
(i)
Self weight (DL),
(ii)
Live Load (LL),
(iii)
Construction Loads (incorporated in LL),
(iv)
Loading due to Differential Temperature rise and fall between shell
and beam elements (TL),
(
i) Loads due to mid-plane temperature rise in shell elements (TL),
(ii
) Through thickness Temperature (TL),
(iii
) variation of Temperature along any parallel circle of the dome
(TL)
(iv
) wind Loads (WL),
(v
) seismic loads (SL).
Combinations
of Loading Cases
From.
the above loading cases following loading combinations were obtained
which were critical for the final design forces.
(a)
1.4 x DL + 1.6 x LL
(b)
1.4 x DL + 1.6 x LL + 1.4 x TL
(c)
1.2 x DL + 1.2 x LL + 1.2 x WL
(d)
1.2 x DL + 1.2 x LL+ 1.2 x WL + 1.2 x TL
(e)
1.2 x DL + 1.2 x LL + 1.2 x WL + 1.2 x TL + 1.05 x SL
(f)
9 DL + 1.4 WL
The
final envelope of stresses as derived from the above is shown in
the Figure (2)
Site
Investigations and Foundations
A
number of alternative modes of construction both conventional as
well as non-conventional were studied in detail to evolve the most
suitable method which is economical and speedy. As a result of these
studies, the following sequence and mode of construction was adopted:
(a) Constructing a working platform at lower ring beam level (i.e.
10.82m above the bottom elevation) by cutting and leveling part
of hill.
(b) Drive 32 Nos. piles from this earth platform while the work
on the platform is in progress and construct the lower ring beam
over the top of piles progressively as the piles-are completed.
(c) Concurrently with pile driving and lower ring beam construction,
erect a central tower of steel frames temporary construction) and
lay the upper ring beam at the top of this tower about 28.5m above
the platform.
(d) Erect the reinforcement (longitudinal and transverse) to precise
profile within a tolerance of 25 mm and thus get a skeleton cage
for the dome (see fig. and fig. 5) which was proposed to, be used
for supporting the formwork and progressively the weight of concrete
as it was laid. No scaffolding was thus required.
(e) Concrete the dome in circular lifts of one meter height.
(f)
After completion of the dome concrete, construct the tower structure
over the dome, consisting of square chamber, God's chamber spire
and pinnacle.
(g) Construct the floor and other accessories of the stupa below
lower ring beam after excavating to a depth of 10.8m from the construction
plat form initially left at a relatively higher level for case of
construction.
Upper
Ring Beam
In
the proposed planning for construction of the dome, prior construction
of the Upper Ring Beam was an essential prerequisite.
Form work for the Upper Ring Beam was cast in 20 segments of' ferrocement
moulds each weighing 'y T. Segments were assembled at the site prior
to lifting to the final position at top of the circular tower with
the help of' crane. Reinforcement was installed within this formwork
and the ring beam was concerted (mix with 340 kg/m3 of cement and
admixture 1.2 1/m3. Part of the ferrocement which was to be in contact
with the dome concrete was removed after concerning of the ring
beam the other portion was left in tact.
An
epoxy bonding agent (BONDKOTE) was applied to the outside of the
upper ring beam prior to concerning the joint between the dome and
the upper ring beam to ensure better bond.
Fabrication
and Erection of Skeleton
Reinforcement for the dome was divided into 81 segments for purposes
oI pre -fabrication and erection. Each segment was fabricated on
a horizontal Jig approximately 37 m long set out on a concrete pad
to the true profile of the skeleton components with angle iron elements.
General
In
the traditional method, form work is usually supported on scaffolding
/ pops from the ground, prior to fixing the reinforcement and concreting.
this is time consuming, cumbersome and susceptible to inaccuracies,
developing during erection of steel reinforcement and formwork,
as well as while laying concrete due to end flexibilities, whereas
in the adopted method, the complete ring of the cage had a self
adjusting tendency.
The
various alternatives such as fiberglass, plywood and steel were
studied for the formwork. Finally a decision was taken to use steel
formwork , with suitable bracings , as it was found to be economical.
Fabrication
of panels
2 mm thick M.S. panels duly stiffened with M.S. angles and flats
were fabricated for use as formwork . Seven Jigs were made, with
adjustable vertical RSJs in order to bend the plates to the required
curvatures. Curvature of the plates was retained by tie-bars and
stiffeners welded to the angle iron frame. 12 mm and 13 mm diameter
holes were drilled in the angles and flats for fixing bolts.
Fixing
of Formwork
The
steel panels were fixed to the reinforcement skeleton by using 10
mm dia. Through bolts encased in rubber hoses. The rubber hoses
prevented the bolts from getting embedded in the concrete. The holes
in the concrete formed by removing the bolts and the rubber hoses
were used to fix the bottom edge of the next higher panel in precise
position and to obtain necessary cover to reinforcement within a
tolerance of + 10 mm.
Concreting
of the Dome
..
for the dome shell . Cement content was 320 kg/m3. Weigh batching
was done at the batching and. mixing-plant and concrete was transported
to site in- transmixers. A retarded was used to increase the setting
time.
Placement of concrete was done with the help of skips and crane
in one meter rings. Angle iron tie bars fixed to skeletons during
erection were cut and removed prior to fixing the formwork. Near
the top .where the slopes were rather flat, windows were made in
the exterior shutters to feud concrete. Vibration was done by Poker
Vibrators. Curing of concrete was carried out for 14 days by keeping
gunny bags ver the concrete and spraying water over them. To ensure
continuous availability of water, a temporary water storage was
provided at the top platform. Covering with gunny bags also helped
to prevent to sun concrete from high temperatures during the day
due to direct exposure to sun. Concreting of the dome took about
11 months for completion up to the upper ring beam.
High
standard of quality control and quality assurance was needed and
maintained during concerning to obtain concrete of uniformly high
quality to meet the demanding. Design requirements. Design requirement
was to have concrete of 25 N/mm2 .The actual. strength achieved
was found to be in the range of 30- 35 N/mm 2.
Loads
on the Structure
In
keeping with the cultural traditions of Sri Lanka, it was intended
to build the stup4 near the top of the hill along the Kotmale reservoir
so as to get a full panoramic view of the dam and the reservoir.
After reconnaissance, a suitable area for siting the stupa was selected
and investigations were undertaken for pinpointing the exact location
of the stupa, which was topographically acceptable and geologically
stable.
At
the chosen site, the firm rock was approximately' 12 m below the
intended finished ground floor level of the proposed stupa. The
overlying strata was soil with boulders. It was necessary to found
the stupa over the firm rock foundations. Two alternatives were
possible for this purpose namely:-
(i) Excavate and remove the overburden and build up the substructure
from the rock level up to the desired floor level of the dome.
(ii) Drive piles to the rock and found the structure over these
piles.
The latter alternative was chosen because excessive cutting along
the hill. slope would have caused instability of the hill along
side the proposed stupa requiring expensive and time consuming stabilization
s measures
Piling
After considering various alternatives for the piles, it was decided
to have 32 Benoto piles of' 1090 mm and 1200mm diameter (alternately)
for which the equipment and know-how was locally available.
Presence of boulders in the strata, large diameter piles were piles
were preferred to enable inspection of rock strata at any stage
of driving and easy access for drilling, and removal of blasted
material whenever the boulders were encountered. piles were set
out along the periphery of the intended bottom ring beam of the
dome in a manner that when extended at the top, they could be used
as columns supporting the ring beam 10.8 m above the ground floor
of the finished stupa. The piles thus served -he dual purpose of
structural foundation support and architectural requirement of
columns around the floor of the main hall.
After any pile was driven to the bed rock prefabricated reinforcement
cage was lowered inside the pile casing and the pile was concerted
while pulling out the casing concurrently.
Pile
caps and Lower Ring Beam
The concrete at the top of the piles was found to be invariably
weak due to the formation of laitance. These portions were removed
by breaking and were re-concerted.
When three adjacent pile caps were completed, the piles were joined4
at the top forming a ring beam of size 1090 mm x 1200 mm leaving
suitable starter bars for the dome. A set of curved steel shutters
was fabricated for the inner and outer sides of the ring beam and
was fixed the curve set out on the ground. The reinforcements were
suitably arranged within the shutters on a screened concrete surface.
The mix design used was 25/20s with 320 kgs/M3 of cement with w/c
ratio 0.5 An electric poker vibrator was used for vibration. The
concerning of one unit took approximately 3 to 31/2 hours duration.
lasted of applying mould oil on the steel form work and screed concrete,
a thin Polyphone layer was 'used which was of immense advantage
in removing the form work in a shorter time and to obtain a finer
finish.