ECONOMIC EVALUATION
 
1.    General Approach
 
The economic viability of the Scheme is considered here from the standpoint of the national economy and also from the viewpoint of the farmers. The main criteria from the viewpoint of national economy are: the contribution to national income, and the net foreign exchange earnings (or savings) arising from the Scheme. The important goals of providing employment and of meeting the food requirements the country are also considered.
 
2.    Method of Assessment of Economic Viability
 
The Scheme is defined as including the following activities : the supply of irrigation water to 9C0,000 acres of the arable land by means of reservoirs, diversions, canals and irrigation systems; the production of electric power to be sold at bus bars of the hydropower stations (excluding trans­mission and distribution); agricultural production from farms within the area (produce assessed at its value on the farm) ; housing of the farmers; the provision of extension and other agricultural services, an implementation agency, experimental and model farms, and other free services supplied by Government for the benefit of the farmers; the provision of the basic infrastructure needed to support these activities.
 
All activities outside the Scheme thus defined are considered as indirect effects.
 
Direct effects (benefits and costs) have been examined in detail and used to appraise the Scheme by the calculation of rates of return with as much precision as possible. Indirect effects have only been roughly estimated to show the investment and employment opportunities opened by the Scheme in other sectors. Secondary effects (income effects) have been evoked to indicate the probable overall impact of the Scheme on the economy of Ceylon
.
 
The internal rate of returns has been adopted as an indicator of social profitability from the national economic standpoint.
 
Since the rate of return is itself an interest rate, no such rate need enter its calculation. However. a rate of interest is still useful as a benchmark with which to compare the internal rate of return. To this end, it is proposed to adopt an accounting rate of interest of 10 percent, reflecting the shortage of capital for productive investment in Ceylon
. It-is felt that no project yielding a return lower than 10 percent should be considered as economically viable. A readily acceptable project should yield a markedly higher rate.
 
The internal rate of return has been worked out using costs and benefits estimated on the basis of current market prices (see Table IX-l I) as well as accounting prices (see Table IX—l2).
 
3.   Basis for Accounting Prices (sometimes called shadow prices’)
 
Accounting prices (different from prevailing market and official prices) are used in order to reflect more accurately the value of inputs and outputs to the economy. Thus, to eliminate distort-ions brought about by Government subsidies, agricultural products have, as far as possible, been valued at world market prices; similarly import prices have been used for fertilizers. Moreover, an attempt has been made at valuing primary factors of production (land, laborer, capital) at their opportunity cost, which should be equal to the value of production foregone by their utilization.
 
Unskilled labour in Ceylon
(including that of the average farmer) and irrigable land in the Dry Zone are at present abundant, and are likely to remain so for a long time. They have therefore been considered as having an opportunity cost equal to zero. But skilled labour is scarce, despite educational and training efforts by the Government. Its opportunity cost has therefore been estimated at twice the prevailing salaries.
 
I.   The internal rate of return may be defined as the rate of interest which, if it were applied to all receipts and expenditure of Scheme (no capital as well as on current accounts), would reduce net benefits to zero.
 
As foreign exchange is very scarce, ii is proposed to adopt, for the purpose of this analysis, an accounting rate of exchange equal to twice the present rate of 5.95 rupees to one US dollar. However, because of lack of reliable data on the import component of certain elements of costs, and of great uncertainties concerning the equilibrium rate of exchange of the Ceylon
rupee, the accounting rate proposed will be used with caution and only to show in what direction and to what extent results ob­tained without it would be modified by its use.
 
4.   Capital Costs
Total capital costs
 
The capital costs of works for irrigation, drainage, flood control and power production for the Scheme as a whole have been estimated on the basis of average prices for construction work currently prevailing on the world market, taking into account the construction of the large works (head works, hydropower stations and transbasin canals) by foreign contractors.
 
The total capital expenditure has been summarized in Table IX-1, distinguishing between the Scheme itself and the economic activities resulting directly from the Scheme.
 
The cost of irrigation systems includes land development work (e.g. clearing and leveling) and the irrigation works required for water deliveries to the farmers’ fields.
 
The settlement cost includes the cost of farm buildings and farm working capital; capital expenditure relating to agricultural extension and other free services and facilities provided by the Government such as model farms, experimental stations, colonization officers’ quarters, wells, village streets, community centre, etc.
 
Costs retained for direct benefit/cost calculations
 
Revenue-earning Government activities related to land settlement that may be considered as having their own economic justification have been excluded from the direct benefit/cost calculations made for the Scheme itself. For the same reason, capital expenditures relating to storage, marketing. transportation facilities, and processing industries have been eliminated from these calculations. Similarly only half of the general overhead (infrastructure) cost indicated above has been allocated to the project proper; the rest has been allocated to other productive activities such as marketing and processing.
 
TABLE IX-1
Summary of Total Capital Costs
 

Description                                                                                               Cost
Rs. Million
A.   The Scheme
        Reservoirs, Diversion Works and Power Plants  1,750
Transbasin canals (and pumping stations) ..                                                      1,109
        Irrigation systems                     ..                             ..               ..               ..     1,805
Settlement                               ..                             ..               ..               ..       817
Overheads                               ..                             ..               ..               ..          47
Implementation Agency            ..                             ..               ..                           55
 Total              ..                                                                            5,583

B.      Activities resulting directly from the Scheme                                                            
         Power transmission ..             ..                                             ..               ..        308
Marketing and processing of agricultural products (and
         revenue-earning Government Activities) ..                                                           47
                        .                                                                                                     _____
                        Total                                    ..                                                        1,120
 

Foreign exchange component of capital coats
 
The import component of the capital cost of the Scheme itself ha~ been estimated at 38 percent of total costs, corresponding to the equivalent of Rs. 2,220 million. This proportion varies from 35 percent for the first phase to 42 percent for the second and third phases of development.
 
Phasing of capital expenditure
Capital expenditures for the Scheme itself by phase are summarized below
 
TABLE IX-3
Summary of Total Capital Costs of the Scheme by Phases
 

         Phase                                      Works         Settlement            Implementation             Total
                                                                                   and                      Agency
                                                                             Infrastructure
 

Rs. Million
  Phase I          -~

    
     Project 1           ..               ..         446.7               123.3                        5.7                    575.7
     Project 2           ..               ..         571.0                 99.0                        6.7                    676.7

     Project 3           ..               ..         264.1                 30.5                        2.9                    297.5

     Total Phase I     ..               ..      1,281.8               252.8                      15.3                 1,549.9
 

     Phase I              ..               ..      1,282                  253                         15                    1,550
     Phase II             ..               . .   631                  280                           9                       920
     Phase III            . .              ..      2,751                  331                         31                    3,113
 

     Whole Scheme ..                ..      4,663                  864                         55                    5,583
 
 

5.     Cost Allocation of Multipurpose Units Included in Phase I
 
The cost of a single-purpose irrigation dam has been worked out and this cost is allocated to irrigation. The difference between this and the total cost is allocated to power.
 
 
The question of allocation of any part of the costs to flood control, or to industrial or domestic water supply is ignored, as these are incidental benefits obtained from the units proposed for construc­tion.
 
Polgolla Diversion with underground power plant (35.8 MW) and tailrace tunnel is estimated to cost Rs. 97.4 million, of which Rs. 29.0 million are towards items like penstock, turbines, power­house, power plant, switchyard and equipment which are directly allocated to power. The balance of Rs. 68.4 million is allocated to irrigation.
 
Bowatenna power plant (3.7 MW) is located at the end of the tunnel which forms pan of the PK canal (Polgolla-Kala
Oya Canal
). This power plant is estimated to cost Rs. 7 million; the whole cost is allocated to power.
 
Victoria Falls hydropower sc/seine (120 MW) is estimated to cost Rs. 247.2 million, of which Ps. 1 28.0 million are for items like penstock, power plant, etc. which are directly allocated to power,
 
I.   Allocation of cost of multipurpose dams can be done it many ways. The above method is one extreme in which the maximum amount is allocated to irrigation. An alternative approach would be to consider a single-purpose power dam, the cost of which could be allocated to power and the difference to irrigation. This would be the other extreme in which maximum allocation is made to power. Thus, it should be recognized that the ratio of allocation of cost of the multipurpose remains an open question and the final ratio to be adopted depends upon the policy of the Government.
 
and the balance of R. 119.2 million are for the darn arid reservoir. It is to be noted that the size of the proposed dam corresponds to N. W. S. (Normal Water Surface) elevation of 1,4 It) feel; whereas for the purpose of irrigation only, it would be adequate to provide a darn with a N.V.S. (Normal Water Surface) elevation of 1,325 feet. The smaller dam would cost Rs. 52.0 million. As the higher dam was selected only from the power point of view, the excess cost of raising the dam, which is (119.2 - 52.0) its 67.2 million is allocated to power.
 
Thus the total cost allocated to power is Rs.(28.0 + 67.2) 195.2 million and the balance of Rs. (247.2 — 195.2) 52.0 million is allocated to irrigation.
 
Moragahakanda hydropower sc/wine (41) MW) is estimated to cost its. 186.6 million, of which Ks. 32.6 million are for items like penstock, power plant, etc., which are directly allocated to power. The balance of Rs. 154.0 million is for the dam and reservoir. The size of the proposed dam corres­ponds to N. W. S. elevation of 640 feet, whereas for the purpose of irrigation only, it would be ade­quate to provide a dam with a N. W. S. elevation of 610 feet. The smaller dam would cost Rs. 122.0 million only. As the higher dam has been selected only from the power point of view, the excess cost 5g raising the darn, which is Ks. (154.0— 122.0) = 32.0 million, is allocated to power.
 
Thus the total cost allocated to power is Rs. (32.6 + 32.0) 64.6 million and the balance of Rs. (186.6— 64.6) = 122.0 million is allocated to irrigation.
 
  Table IX-3 below shows a summary of the allocation to agriculture and power of all capital. costs in the Scheme.
 
TABLE 1X-3
Summary of Capital Costs Showing Allocation

to Agriculture and Power
 
           Phase                                                  Power              Agriculture      Total
                                                                                 Rs.          Million

Phase I                                                           
Project 1                                          36                    540                 576
Project 2                                        195                     481                 676
Project 3                                          65                     223                 298
 

                 Total Phase 1
Phase 1                       296                    1,254            1,550
Phase 11                      22                       898               920
Phase III                    454                    2,659            3,113    
 

Entire Scheme            772                     4,811            5,583
 
 

Current Costs (operation and maintenance)
 
Operation and maintenance expenditure have been estimated in detail for the first phase projects, and are found to be close to the following average values
For dams, hydro-electric stations and transbasin canals           1 percent of the capital cost
For new irrigation systems                                                      2 percent of the capital cost
For existing irrigation systems                                                 3 percent of the capital cost
                                                                       
These percentages have been adopted in determining the current expenditure involved in the operation and maintenance of the whole Scheme.
Current costs relating to housing and general infr4structure allocated to the Scheme, which are relatively small and difficult to estimate, have been omitted.
 
Current costs relating to extension and other services provided free by the Government have been estimated at Rs. 20 per acre per year, on the basis of the feasibility studies of the first phase.
 
Production costs per kWh are approximately estimated at 10 percent of the investment figures (6 percent interest + 3 percent depreciation + 1 percent for operation and maintenance).
The estimated data of the current expenditure involved in the Scheme a whole arc summarized below:—
TABLE IX-4
Current Costs of Scheme
 

                                                    Area under Irrigation                           Operational and                Cost of
Phase                                                                                                     Maintenance Costs          Extension         Total
                                                    ---------------------------------- ------------------------                              Services
                                                    Existing        New              Total       Irrigation     Power              

 

                                                    (1,000 acres)                                                                                    Rs. Million
 
I                        ..                                         ..                                          144.2             184.1           328.3           15.6             3.1                 4.6                   32.2
II                     ..                                            ..                                                20.8              209.0           229.8           11.06           0.21               4.3                  15.57
III                    ..                                            ..                                                 81.2             260.7           341.9           31.53           4.49               6.03                42.05


Whole Scheme            .
                                            246.2             653.8          900.0       58.19          7.8               14.93                80.82
 
 

7.   Benefits
 
The benefits of the Scheme are essentially derived from the sale of agricultural products and electric power. Benefits derived from flood protection of presently settled land and of cities, as well as from the rental value of houses to be built for the settlers, are small and difficult to estimate. They have been omitted.
 
           Benefits may be defined as the value of production minus the current costs involved in obtaining it.
 
           From a national economic viewpoint, and using the shadow prices indicated above, production benefits used to calculate an internal rate of return may be considered as close to the value added (V)’ concept of national account. As regards farm benefits, the identity is complete (leaving out foreign exchange complications) for skilled labour, for which an opportunity cost equal to twice its. Market value is assumed.
 
The identity may also be considered as complete for electric power production, neglecting the relatively small importance of skilled labour in operation and maintenance costs. “Value added” is therefore used in the national accounting to measure agricultural and electric power benefits from a national economic standpoint.
 
1.             V =. value of production minus value of goods and services purchased from “other enterprises” remuneration  of primary factors (national resources, labour and capital) plus taxes.
Agricultural benefits
Value added by agricultural production is given below for each phase of the Scheme.
 
TABLE IX-5
Value Added by Agricultural Production
 

                                                           With Minor                                with Major
                                                       Improvements in                         Improvements in
Phase                                                 Agricultural                                 Agricultural
                                                             Methods                                     Methods
 

                                                                                        Rs. All/lion
Phase I Project1                                       128                                             167
            Project 2                                        99                                             130
            Project 3                                        37                                              47
 

Total Phase I                       -                    264                                            344
Phase II                              -                    303                                            369
Phase III                             . -                  494                                            607
 

Entire Scheme                   ..                1,061                                         1,320
 

The figures correspond to two different levels of yields defined as :
 
      Better yields, attainable almost immediately after land development and settlement because they require only the adoption of minor improvements in farming practices, which could easily be introduced in a climate of change, with the assistance of the recommended dense network of extension assistance.
 
High yield requiring major improvements in farming practices, which could only be introduced progressively over 5-10 years.
 
For the economic evaluation, it is assumed that major improvements will not be adopted before 1981.
 
To take account of possible delays in land settlement and in adoption of the improved agricultural practices recommended, it has been assumed that agricultural production will increase in the following manner after commissioning of a given irrigated area
                                                                                    Percentage of attainable
Year                                                                             agricultural output on the
               irrigated area
 
0 (year of commissioning)                                                           5  percent
1                                                                                              33  percent
2                                                                                              67  percent
3                                                                                              90  percent
4 (and following years)                                                            100  percent
 
Net agricultural benefits, after deduction of various related current costs of the Scheme, are given below for each phase. These current costs have been deducted fully on the simplifying assumption that they reflect the opportunity cost to the community of the services they provide.’
_______________
 
1.  A preliminary analysis of these costs, considered as a whole, has shown that this assumption is valid, as skilled labour constitutes approximately 50 per cent of the total wage bill and it has been assumed that the accounting price of skilled labour is twice its market value, and that of unskilled labour is zero.
 
TABLE IX-6
 
Net Agricultural Benefits with Major Improvements in Agricultural Methods
 

                                            Value Added by        Operation and             Extension
Phases                                  Agricultural           Maintenance of             and other                Total            Agricultural
                                              Production             irrigation Works            Services             (rounded)       Benefits
 

Rs. Million
I                                                        344                           15.6                          4.6                            20                        324
11                                                      369                           11.1                          4.3                            15                        344
III                                                      607                           31.5                          6.0                            38                        569
 
 

Net agricultural benefits with minor improvements in agricultural practices are similarly given below for Phase I
 
 
                                                                                      TABLE IX-7
 
Net Agricultural Benefits with Major Improvements in Agricultural Methods in Phase 1
 

                                            Value Added by Operation and                    Extension            Total               Agricultural
Projects                              Agricultural Maintenance of                        and other
                                              Production Irrigation Works                       Services              (rounded)       Benefits
 

                                                                                                                  Rs. Million
         1                                           128                                 7.3                          2.3                            10                        118
         2                                             99                                 5.5                          1.6                              7                          92
         3                                             37                                 2.8                          0.7                              3                          34
                                                      264                               15.6                          4.6                            20                        244

                                                                                 
Electric power benefits
 
Benefits derived from the generation of hydro-electric energy have been estimated as follows:
only firm power has been taken into consideration, non-guaranteed power being of little value, as its use presupposes the presence of standby thermal plants.
 
The value of one kWh of firm (guaranteed) energy to the economy has been estimated, on the basis of accounts of the Department of Government Electrical Undertakings, at 6 Ceylon
cents. -
 
 
TABLE IX-8
 
Power Benefits by Phases
 

                                                                    Firm                        Sales              Operation and
                    Phases                                  Energy                    Value          Maintenance Cost             Benefits
 

kWh million .                                                                                                                    Rs. Million

 

Phase I
                        Project I                  ..                                                          202                  12.1                          0.4                              11.7
                        Project 2                 ..                                                          469                  28.1                          2.9                              26.1
                        Project 3                 ..                                                          149                    9.0                          0.7                                8.3
                    Total Phase I             ..                                                          820                  49.2                          3.1                              46.1
                    Phase II                      ..
                                                                47                    2.8                          0.2                                2.6
                    Phase III                     ..
                                                 1,169                  70.1                          4.5                              65.6
 

                             Grand Total ..                                                           2,036               132.1                          7.8                          114.3

 
 

Total benefits
 
Total benefits, with major improvements in agricultural practices, are estimated below by phase.
 
TABLE IX-9
 
Total Benefits with Major improvements an
Agricultural Practices
 

                                                                                       Flood
            Phase         Agriculture               Power           Protection 1                           Housing                Total

                                                                                                         
                                                                                   Rs. Million
 
           1                  324                       46                                                           370                                    
               II                 344                          3                                                          347                                                
III                569                       65                                                           634
 

Total         1,237                       114                                                        1,351
 

 Pro  memoria.
 
 
Total benefits with minor improvements in agricultural practices are estimated for Phase I:
 
 
TABLE IX- 10
 
Total Benefits with Minor Improvements for Phase I
 

Projects               Agriculture               Electric Power                         Total

Rs. million
            1                              118                                               12                     130
            2                                92                                               26                     118
            3                                34                                                 8                      42
     

   Whole Phase              244                                               46                     290
        
8. Profitability
 
Profitability has been considered both from an overall economic and from a private financial point of view.
 
Social profitability
 
Social internal rates of return and some other indicators of social and financial profitability, based on costs and benefits already discussed above, are given in Table IX-1 I for the Scheme as a whole, for each of the three phases, and for the three projects of Phase I.
 
A study of this Table leads to the following conclusions.
 
           With a social internal rate of return of 15 percent and a capital/benefit ratio slightly above 4, the Scheme as a whole may be considered economically sound.
 
           The rates of return and capital/benefit ratio calculated for the first and second phases appear quite satisfactory. However, the unit cost of agriculture in the third phase appears to be above normal (a 1,480 per acre), for which reason its rate of return is almost at the lowest limit (12 percent).
 
This result has been obtained using the present exchange rate of the Ceylon Rupee. Had the accounting rate proposed earlier (of twice the present official rate) been used, the rate or return would have been raised by several points (see Table IX-12). Although “shadow pricing” in this field is subject to great uncertainties, such considerations should prevent excessive pessimism regarding the level of the rates of return.
   
            In the first phase, attention is attracted by the relatively high cost of agriculture tender the second and third projects, which is the result of the incomplete utilization of the irrigation potentialities provided by Victoria and Moragahakanda reservoirs. With the realization of the second phase or development, based on these water sources, the indicators of Projects 2 and 3 improve considerably and their rates of return rise respectively to ii and 14 percent.
 
Private financial profitability
 
On the basis of “guaranteed prices” for farm products it is estimated that the average net farm income in the area of the Scheme will be raised from the present low level of about Ks. 600 to approximately Rs. 1.344) with minor improvements in agricultural practices, and to Ks. 1,840 with major improvements. With the completion of the Scheme, at least the latter level should be obtained over the entire area of the Scheme.
 

TABLE IX-11

 

Indicators of Risibility for the whole  scheme

 

(Market prices ,in round figures)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Annual benifts

 

Capitoal benfitRatio

Social Internal Rate of Return

Unit Capitol Cost

 

Phases

Capitol Cost

Total

Agri cultrue

Power

Total

 

Total

Agricultrue

Power

Agricultrue

Power installed Capacity

 

projects

Agricultrue

Power2

 

 

 

 

 

 

 

 

 

Rs. million

 

 

 

 

 

precent

Rs/acre

Rs/kw

 

I

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1

540

36

576(a)

188

12

130

 

4.4

4.6

3.0

17

4,690

900

 

 

 

 

     (b)

157

12

169

 

3.4

3.4

3.0

 

 

 

 

2

431

195

676(a)

92

26

118

 

5.7

5.2

7.7

13

6,170

1,630

 

 

 

 

      (b)

123

26

149

 

4.5

3.9

7.7

 

 

 

 

3

233

65

298(a)

34

8

42

 

7.1

6.9

8.1

12

6,850

1,630

 

 

 

 

      (b)

44

8

52

 

5.7

5.3

8.1

 

 

 

 

Total

1,254

296

1,550(a)

244

46

290

 

5.3

5.1

6.5

14

5,500

1,480

 

 

 

 

        (b)     

324

46

370

 

4.2

3.9

6.5

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

II

898

22

920(a)

288

3

291

 

3.2

3.1

7.3

20

4,180

1,465

 

 

 

 

     (b)

344

3

347

 

2.7

2.6

7.3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

III

2,659

454

3113  (a)

456

65

521

 

6.0

5.8

7.0

12

8,830

1,550

 

 

 

 

     (b)

569

65

634

 

4.9

4.7

7.0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Grand Total

4,811

722

5583(a)

988

114

1,102

 

5.1

4.9

6.8

15

6,470

1,520

 

 

 

 

     (b)

1,237

114

1,351

 

4.1

3.9

7.0

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.Costs as worked out for a single  purpose irrigation scheme

 

 

 

 

 

 

 

 

 

2 Total costs minus costs allocated to irrigation

 

 

 

 

 

 

 

 

 

 

3 including settlement, overheads and implementation agency for equivalent area

 

 

 

 

 

 

4 Marginal costs only.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(a) with minor improvements in agricultural practices.

 

 

 

 

 

 

 

 

 

(b) with minor improvements in agricultural practices.

 

 

 

 

 

 

 

 

 
 
 
 
Assuming farms of five acres for families of 6.5 persons, these levels of farm productivity would correspond respectively to per caput incomes of Rs. 1,030, and Rs. 1.420. The figures compare favorably not only with the present average per caput income in Ceylon
(Rs. 655) but also with tenta­tive projections in this magnitude for the year 1990 (Rs. 1,000).
 
Such levels of income should make it possible for the farmers to contribute financially to the Scheme in the form of payments for water rights and for the progressive purchase of their lands and houses.
 
TABLE IX-l2
 
Indicators of Profitability for Phase 1
(Accounting prices, in round figures)
 

                                                 Capital Costs                                          Annual Benefits
                         -------------------------------------------------             -----------------------------                   Capital           Social
Projects           Works         Settle-      lmplemen-                     Agricul-    Power     Total              Benefit          Internal
                                              ment              tation          Total          ture                                              Ratio              Rate of
                                      Irrigation      Agency                                                                                                               Return

                                                                               
                                                                                Rs, million                                                              Percent
 
       I                  581               139                    7                727          207              18            225              3.2                     21
       2                  789               103                  10                902          162              36            198              4.5        
-                                15
    
3                  362                 35                    4               401         59              13              72              5.6                     15
 

Total                                                                              2,030                                             495
 
 

9.    Effects of Devaluation
 
Devaluation of the pound sterling in 1967 was followed in Ceylon
by devaluation of the rupee (22nd November, 1967
) by 20 percent. The official rate before devaluation was U.S. $ 1.00 = Rs. 436 and £ I = Rs. 13.33. The rate has now been fixed at U.S.
sl.00 = Rs. 5.95 and £ 1 = Rs. 14.20.
 
The effect of devaluation on the costs and benefits of the Scheme may be roughly estimated as follows:-
 
(i)   Costs (capital and current)
 
   considering the probable sources of imports and expected changes in prices, the foreign exchange component of costs, expressed in rupees, must be increased by 20 percent
 
   taking account of the probable incidence of the devaluation of the rupee on local prices, total costs in rupees (foreign exchange and local currency components) will increase by approximately 15 percent.
 
(ii)   Benefits (sales value)
 
   benefits resulting from sales abroad and/or estimated at world market prices will increase by 20 percent.
       benefits from total sales will increase by 17 percent.
 
These relatively small differences (between the effect of devaluation on costs and its effect on benefits) will slightly increase the internal rates of return, but the increases, very much inferior to one percent, may be considered negligible. The recent devaluation of the Ceylon
rupee will not therefore significantly alter profitability indicators.