IMPLEMENTATION PROGRAMME FOR 1976
 
Stage II (26,000 acres) (112, 117 and H9)
Development Programme
 
The programme for 1976 envisages the development of 26,000 acres of farmland, thereby enabling the re-settlement of about 10,000 farm families. The 26,000 acs. will be located in Areas H1, 112, 117, 119 as shown in the annexed Plan. The irrigation Blocks that will be developed are as given below—
 

AREA                          Block No.      Acreage          Total               Remarks

 

H – 1                                  305                1,000             1,000               Balance of H – 1
H – 2                                  305                   600                    
                                           306                1,540
                                           307                   740
                                           309                1,350
                                           310                1,000
                                           311                   760
                                           312                1,290
                                           313                1,410
                                           314                3,250            11,940
 
H – 7                                  101                1,740
                                           102                1,620
                                           103                2,160
                                           104                2,580             8,100
                                               
H  - 9                                  201                1,137
                                           202                1,530
                                           203                1,485
                                           204                1,443
                                           205                   870             6,465

                        

Total (Approx.)          27,505*
 
 
  • Figures are approximates. Final figures likely to be about 26,000 acres.
 
v It is intended to settle farmers once every quarter of the year and to make land available for cultivation at the rate of about 6,000 acres per quarter.
 

Work to be executed

 
(1) Engineering
 
            The main items of work to be executed for the development of the acreage as given in the programme would be as follows:-
 
i)                    LB Main canal from Mulannatuwa to Maha Katnoruwa.
ii)                   Completion of Branch Channel No. 1 m Kalawewa LB.
iii)                 Branch Channel No 2 inclusive of extensions that may be necessary.
iv)                 Improvements to Maha katnoruwa Tank
v)                  Construction of distributary channel in Blocks 305, 306, 307, 309, to 314
vi)                 Extension of RB Main Canal of Kandalama up to end.
vii)               Randeniwewa, Mahawewa and Mandawela Tanks.
viii)              Branch Channels in Areas H7
ix)                 Distriubutary Channels in Blocks 101, 102, 103 and 104.
x)                  LB Main Canal from Dambulu Oya Reservoir.
xi)                 Branch Canals in H9 Area.
xii)               Distributary Channels in Blocks 201, 205.
xiii)              On farm development work for 26,000 acres.
xiv)             Drainage channel improvements in Areas H1, H2, H7 and H9.
xv)               Dambulu Oya Reservoir.
xvi)             Kalawewa RB sluices and RB Yoda Ela (to be completed in 1977)
xvii)            Permanent buildings for operation, maintenance and general purposes.
 
Detailed quantities are given in Annex.
 
2.1   Selection and training of 6,000 farmers
2.2   Settlement of 10,000 farmers
2.3   Extension work to enable the 10,000 farmers to commence cultivation during the year.
 
4.  Investigation, Planning, Designs and Co-ordination
 
            The irrigation Department and Mahaweli Development Board would provide the necessary engineering services. All kalawewa   works would be handled by Irrigation Department except for the Kalawewa RB sluice. All works on H7 and H9 Area would be handled by Mahaweli Development Board except for the Kandalama RB Main Canal extension.
 
5.  Supervision of Construction
            The supervision of construction will be carried out by the Mahaweli Development Board. For this purpose, construction sub offices will be established as follows.
 
(a)    Area H2
 
Work will be supervised from Kulannatuwa office. A field office (without residential facilities) will be established in Block 309.
 
(b)   Area H7
A construction camp and office will be established near Madutugama.
 
(c)  Another sub-office on the main Dambulla-Kekirawa Road
will be established at Keki­rawa for Area H7 development.
 
(d)  A construction camp and office is being established at Halmillawa for development of Dambulu Oya Reservoir and Area H9.
 
The buildings that would be put up in these construction camps, wilt be of a permanent type and that they could be used for future operation and maintenance of the project.
 
6.   Construction Agencies
 
It is expected that Construction Agencies would undertake work during 1976, as tabulated in Annex. II.
 
7.   Finances
 
Total finance required is Rs.245.5 million (excluding FEECs) out of which Rs.40 million will be in foreign currency.
 
The draft budget for 1976 has the following provision for Stage II:—
 

Local Currency                                       84.0           
Foreign Currency (Free Exchange)           10.0          This amount is only for the import of spare
                                                                              required for the available construction machi­
                                                                              nery. No provision for the import of new
                                                                              equipment.
FEECs                                                     6.0
Total (Rs. M)                                        100.0
 

Further amounts of local currency can be made available as necessary.
 
8.   Problems in Implementation
 
The main problems in implementing the programme of work are as follows:—
 
I.    Each State Organisation listed in Annex LI should be firmly committed to deliver the output expected. If such involvement is not forthcoming, the programme cannot be undertaken.
 
2.    Land preparation work cannot be undertaken as suitable machinery will not be available. Trials should be carried out in 1975 with existing machinery and arrangements made to procure machinery before January 1976. Tentative estimates indicate that 32 Nos. D7 Tractors with rippers and 160 Nos. “4000” Farm Tractors with 3 disc ploughs are required.
 
3.    Plans and proposals for the provision of general facilities such as Postal, Educational, Health, Transport, etc. have not been finalised for implementation during 1976. Some definite action has to be taken immediately.
 
4.    All acquisition for the 1976 programme has to be the responsibility of 0. AX, Anuradha­pura
and Kurunegala. An organization for the speedy execution of acquisition work has to be set up.
 
9.   Settlement
 
Apart from the 26,000 acres of irrigable area, and additional 7,500 acres have to be developed to provide homesteads, hamlet centres, village centres, centres for community facilities, etc.
 
Obtaining way leave, acquisition of private lands, re distribution of private lands, selection and settlements of farmers, provision of community development, marketing and credit facilities to the farmers to be done by Mahaweli Development Board.
 
In view of the volume of work involved in 1976 programme, it is essential that a number of officers experience in Land Administration, specially at senior staff level are obtained.
 
9.       Main Quantities of Work in Areas H2, H7, H9
 
 

                                                                Earth work Cu. Yds.             Rock Cu. Yds.                      Concrete

                                                                                                                                                                Cu Yds.
                                                                Machinery    Manual    Machinery  Manual    Large      Small
 

Kalawewa LB Main Canal
     Mulannatuwa to Maha-
     Katnoruwa               ..              ..             350,000                                 35,000                   -           3,300              200
Branch Canal No. 1      ..              ..             230.000                       -           5.000                   -           1,900              100
Branch Canal No. 2      ..              ..                         -           165,000           3,500                   -           1,100              100
Improvement to Mahakatnoruwa
     Tank                          ..              ..             130,000                       -                   -                   -            1500                   -
Distrubutary Canals                    ..                         -           600,000                   -         84,000                   -           8,000
Field Canals                  ..              ..                         -           205,000                   -                   -                   -         10,000
Land Leveling               ..              ..             800,000        1,200,000                   -                                       -                   -
Roads                             ..              ..             350,000                       -                   -                   -                   -              600
Drainages                      ..              ..             240,000           360,000                   -                   -                   -                   -

  Total                             ..              ..          2,100,000        2,530,000         43,500         84,000           7,800         19,000
 

Area H1 – 1,000 Acs.                          (Part 305)
Distributary Canals      ..              ..                         -             50,000                       -           7,000                   -          700
Field Canals                  ..              ..                         -             17,000                       -                   -                   -          800
Drainages                      ..              ..                         -             20,000                       -                   -                   -               -
Land Leveling               ..              ..               67,000              78000                       -                   -                   -               -
Roads                             ..              ..               23,000                       -                       -                   -                   -          100

     Total                          ..              ..               90,000           165,000                       -           7,000                   -       1,600
 
Area H7 – 8,000 Acs.
Extension of Kandalama RB
     Main
Canal
up to 22 M          ..             750,000                       -         19,000                   -           3,600              200
Improvement of Tanks                ..             230,000                       -         11,500                   -           1,000                   -
Branch Canal                ..              ..                         -             50,000                   -           1,000                   -              400
Distrubutary canals     ..              ..                         -           400,000                   -         56,000                   -           5,600
Field Canals                  ..              ..                         -           135,000                   -                   -                   -           6,400
Drainages                      ..              ..             160,000           240,000                   -                   -                   -                   -
Land levelling
                                        ..              ..             540,000           620,000                   -                   -                   -                   -

Roads                             ..              ..             100,000                       -                   -                   -                   -              300

     Total                          ..              ..          1,780,000        1,445,000         30,500         57,000           4,600         12,900
 
Are H9 – 6,000 Acs.
Dambulu Oya Reservori              ..          1,300,000                       -         31,000                   -           3,500                   -
LB Main
Canals            ..              ..             145,000                       -         20,000                   -           1,400              100
Branch Canals              ..              ..             100,000           100,000                   -         10,000           1,400              100
Improvement of Tanks                ..               60,000                       -           1,000                   -           1,500                   -
Distributary Canals      ..              ..                         -           300,000                   -         42,000                   -           4,000
Field Canals                  ..              ..                         -           100,000                   -                   -                   -           4,800
Drainages                      ..              ..             120,000           180,000                   -                   -                   -                   -
Land levelling               ..              ..             300,000           500,000                   -                   -                   -                   -

Roads                             ..              ..               525,00                       -                   -                   -                   -           1,000
     Total                          ..              ..          2,550,000        1,180,000         52,000         52,000           7,800         10,000

 

Kalawewa RB Yoda Ela
Improvements to Kalawewa RB
Yoda Ela 0-5 mls.          ..              ..             250,000                       -         15,000                   -           2,300              200
 
 

Jungle Clearing
 

                                                                                           Heavy             Medium              Light
                        Area                                                            Acs.                   Acs.                 Acs.
 

                   H2                                         12,000 Acs.   ..                                                                                      3,500                 5,500                 8,000
                   Hi
                                        1,000 Acs.   ..                                                                                               800                    300                    600
                   H7
                                              8,000 Acs.   ..                                                                                               500                 5,300                 1,700
                   H9
                                              6,000 Acs.   ..                                                                                      1,500                 4,400                 1,700

                       
                        Total         ..                                                               ..                                                                                      6,300             15,500            12,000
 
 

Future Programme for Stages H & UT of Project I
 
Detailed implementation programmes will be prepared for the development of the 39,000 acs. yet to be developed under Stage II in areas H4 and H5 in the Kalawewa Right Bank. These will be irrigated by means of an extension from the right bank main canal
of Kalawewa
(which will be widened and straightened for this proposes). It is proposed to complete those developments by the end of 1979.
 
A preliminary investigation report has been prepared for the development of 8,000 acs. Under Kantalai Tank including 6,500 acs. of Sugarcane f paddy under Stage LI A. This and 1,500 acs. is the part of Stage III that will be taken up first in order to give high priority for sugar production. This will enable the surplus capacity of the processing facilities at the Kantalai Sugar Factory to be fully utilized and thereby the sugar industry will be more economical. This work will also be commenced during the period 1977-79. The balance 12,000 acs. of new lands under Kaudulla in Stage III will be taken up thereafter. Detailed programmes for these works will be worked out before implementa­tion. About 60% of these areas (other than 8,000 acre area under Stage III A) will be developed for highland crops and the balance 40% of lands will be used for lowland paddy.
 
 

 

 

Earthwork

Millions of

Cu. Yds.

Rock Excavation

Thousands of

Cu. Yds

Concrete

Thousands of

Cu. Yds

Jungle Cleaning

Thousands of Acs

Remarks

Machine

Manual

Machine

Manual

Large

Small

Heavy

Medium

Light

1.        RVDB

 

 

 

2.        SD & CC

 

 

3.        SEC

 

 

 

 

4.        ARMY

 

 

 

 

5.        TCEO

6.        Contractors

        Large

        Scale

 

 

7.        Job contractors

 

 

8.        Group of villagers

 

9.        Land Dev. Dep

 

 

10.     Dept. of Mach & Equip

 

 

(a)

 

(b)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(a)

(b)

2.55

 

0.23

 

0.22

 

 

-

 

 

 

 

0.48

0.65

 

 

 

 

1.70

0.25

 

 

 

-

 

 

 

2.37

 

-

1.180

 

 

 

 

 

 

-

 

 

 

 

 

 

 

 

 


0.33

1.445

 

 

 

 

-

 

 

 

 

 

-

52

 

 

 

 

 

 

-

 

 

 

 

 

 

 

 

 

 

30.5

15.0

 

 

 

-

 

 

 

 

 

-

 

 

 

43.5

52

 

 

 

 

 

 

-

 

 

 

 

 

 

 

 

 

91

57

 

 

 

 

-

 

 

 

 

 

-

7.8

 

 

 

 

 

 

8.0

 

 

 

 

 

 

 

 

 

7.8

 

4.6

2.3

 

 

-

 

 

 

 

 

-

10.0

 

 

 

 

 

 

-

 

 

 

 

 

 

 

 

 

20.6

 

12.9

0.2

 

 

-

 

 

 

 

 

-

-

 

 

1.3

 

 

 

-

 

 

 

 

 

3.0

 

 

 

 

 

0.5

 

 

 

-

 

 

 

 

 

 

 

 

 

0.3

-

 

 

1.3

 

 

 

-

 

 

 

 

 

4.5

 

 

 

 

 

5.3

 

 

 

-

 

 

 

 

 

 

 

 

 

3.0

-

 

 

1.3

 

 

 

-

 

 

 

 

 

7.0

 

 

 

 

 

1.7

 

 

 

-

 

 

 

 

 

 

 

 

 

0.7

(a)      All works in H9 Area except jungle        

         clearing and land leveling

(b)     Branch Channel No. 1 in H2 area. Jungle

clearing in H2 area  and land leveling in

same are (Residual work in allocation to

Army)

(a) Completion of Kalawewa Head              works

( b) Bridge across Kala Oya on Baduluwewa

- Andarawewa Road

 

All jungle clearing and machine work in

Land leveling 10,000 acs. of land in H1 &

H2 areas.

 

Work in H1 & H2 Areas

 

(a)      All work in H7 area.

 (b) Work on Kala Oya RB channel to be  undertaken after H7 area is organized

 

To be given work by assigned agencies as and when found necessary.

Work in H2 Area.

 

Programme does not include buildings       

for Health, Education, and Postal Depts.

 

Jungle clearing in H9 Area. Rock .

Blasting in H2 Areas

 

 
                                                                   NOTES :             (1)          SD & CC will establish a concrete yard for recasting small structural units
                                                                                                 (2)          Agencies to construct roads and drainages in Area H2 yet to be assigned.
                                                                     (3)          Agencies to clear balance jungle in Area H9 and land leveling work in the same    area
                                                (60,000 acs ) yet be  assigned.