Volume II
 
FEASIBILITY REPORT
FOR PHASE I OF DEVELOPMENT
 
 
PROJECT 1: POGOLLA DIVERSION
 
1.    General Scheme of Water Distribution
 
The Water supply is derived from the how of the Mahaweli Ganga and Amban Ganga in their upper reaches and also from the local yield which is regulated in the reservoirs and smaller tanks in the systems D-l and Ii.
 
The main water source is the Mahaweli Ganga, from which a maximum discharge of 2,000 cusecs is diverted through the Sudu Ganga into the Amban Ganga by the diversion structure and tunnel at Polgolla.
 
The diverted Mahaweli flow, supplemented by runoff in the catchments of Amban Ganga itself, is bifurcated as described hereunder
 
A discharge of 1,300 cusecs (maximum) is sent farther down the Amban Ganga and divert­ed at the Elahera anicut through ElaheraMinneriya - Kantalai-Yoda Ela (EMYE) canal to Minneriya and from there to Kaudulla and Kantalai tanks, which supply water to system D-l (system C is irrigated directly from the EMYE canal).
 
The remaining 700 cusecs is transferred through the Polgolla-Kala Oya canal (P.K.) to Kalawewa and Kandalama tanks, from which 70 percent of system H is irrigated.
 
The irrigation water supply is assured for 85 percent of years as determined from the 20-year runoff records.
 
2.    Polgolla Hydraulic Unit
 
The Polgolla hydraulic unit includes a barrage across the Mahaweli Ganga, a tunnel connecting the Mahaweli to the Sudu Ganga, and a hydro-electric power station.
 
Geological conditions at th3 proposed sites can be rated as favourable. At the dam site, at a depth of 20-30 feet below the surface sand and highly-weathered formation, there are hard quartz­-biotite granulites which can serve as a reliable .foundation for the hydraulic structure. The tunnel axis is laid through fresh quartzitic and quartz-biotite gneisses, granulites. and quartzites, in which layers occur at an angle of 20-60 degrees to the tunnel axis and dip at 70-90 degrees. There is the possibility of crossing several closed faults which date as far back as the age of the geologic formation. The slope in the Sudu Ganga valley, where the tunnel has its outlet, is covered to a depth of 80 feet by loosely fragmented sediments and layers consisting of granulites and crystalline limestone of decom­posed and crushed texture. These layers are under laid by slightly weathered and fresh rocks.
 
The alternative studied for the structural arrangements of the unit were
 
(i)    A free-flow tunnel and an underground hydro-electric station at the beginning of the tunnel, producing an energy output of 18.3 million kWh at a cost of Rs. 83 million (pre-devaluation rate).
 
(ii)   A pressure tunnel with a ‘surface’ hydro-electric station at its end, on the bank of the Sudu Ganga, giving an energy output of 192 million kWh at a cost of Rs. S8 million.
 
The alternatives are very similar in benefits, and the first is cheaper by Rs. 5 million, which is less than 10 percent of the cost and within the range of tolerance. The economic appraisal in this report favours the first alternative. but since the alternatives do not differ in principle, the final selection car. be left; for the final stage of designs. when detailed investigations will permit a more accurate assessment. If the costs and benefits are still found to be very similar, the second alternative is to be preferred.
 
The items contained in the hydraulic unit are described briefly below
 
(i)    The barrage will be a concrete dam with sector gates and have a maximum head of 25 feet. It will be 530 feet long at crest level and will be capable of coping with a discharge of  203,000 cusecs this being a flood of 1,000 years frequency. This discharge can pass through the barrage, when the gates are open, without causing any change in the normal conditions upstream.
 
(ii)   The underground hydro-electric station, which will have four installations with a total capacity of 35.8 megawatts, will be located at the bottom of vertical shaft 230 feet below the normal water surface elevation. The net guaranteed head is 256 feet. The discharge taken through turbines is variable. Thus, for 40 percent of the time the operating flow will be at its maximum of 2,000 cusecs; for 70 percent of the time the discharge will be over 1,000 cusecs.
 
The average annual firm power capacity at a flow of 90 percent frequency will be 21 megawatts, with an energy output of 183 million kWh per year. In the dry months (January to May) the monthly firm power capacity will be reduced to 10-14 megawatts. While in the wet months (October to December) it will reach the maximum of 35.8 megawatts. The seasonal fluctuation in firm power capacity should be taken into account when. Establishing the consolidated operation graph of the available power system., After 1976, decline in power generation at Polgolla hydro-electric station during the dry months will he compensated for in great measure by a controlled regime of operation during this period at Victoria hydro-electric station.
 
(iii)   The tunnel will be of horse-shoe section, 18 feet in diameter, and lined with concrete; its length will be 26,150 feet.
 
The total cost of the hydro-unit will amount to Rs. 97.44 million (post-devaluation), of which the foreign currency allocation will be Rs. 56.44 million leaving 41.04 million required in local currency. Distribution of costs by utilization criteria allows Rs. 68.4 million for irrigation and Rs. 29.0 million for power production. Annual cost of operation and maintenance adds up to Rs. 974,400 estimated at one percent of corresponding capital expenditures. The sales value of one kWh at the bus bars of the hydro-electric station has been estimated at 5.9 Ceylon
cents (pre-devaluation) and 6.0 cent (post-devaluation).
 
Commissioning of Polgolla hydro-electric station in the National electric-power grid will require construction of 2.5 miles of DC 132 kilovolts transmission, at a total cost of Rs. 456,000. This expenditure is classified as indirect and is included in the economic evaluation.
 
3.   Stabilisation of the Sudu Ganga Channel
 
Stabilisation of the Sudu Ganga channel will prevent its erosion and active silting of the reser­voir proposed at Bowatenna. The stabilisation will be done by removing irregularities from the river gradient in the reaches where scouring is possible. This will be achieved by building drop structures, straightening sharp bends in the river, and training the bed and the banks suitably with river profiles of masonry and rip-rap protection.
 
Its proposed to carry out the river training in two steps, the first step to include straightening and stabilisation of the channel to take the design discharge; and the second, with further improvements, to be undertaken after three to five years of operation under the new conditions.
 
The cost of the first step is estimated at Rs. 5,700,000 and the second step is expected to cost l(s. 4,901,000, making a total cost of Rs. 10,610,000. The operation and maintenance cost is estimated at Rs. 106,100 per year.
 
4.   Elahera-Minneriya-Kantalai-Yoda Ela (E.M.Y.E.) Canal
 
The Elahera.Minneriya.Kantalai-Yoda Ela canal, constructed several centuries ago, has been restored and partly remodelled in the, past twenty years. The canal begins at the Elahera anicut, on the Amban Ganga, and flows along a contour to the existing Minneriya tank Issuing again from the Minneriya tank, it passes above the Kaudulla tank, augmenting the latter through a special feeder, and spills into the Yoda Ela canal, which leads to the Kantalai tank.
 
The present conveyance capacity of the canal is 1,000 cusecs in the first 4.9 miles.1,250 cusecs from mile 4.9 to mile 6.3, 1,500 cusecs from mile 6.3 up to the Minneriya tank. In the first 1,000 feet of its run, the canal crosses rock structure and is lined. Farther on it goes through earth soils and is guide by an earth bund on the downhill side. On the uphill side, the canal is open for intercepting the flow of the streams that drain its catchment area. Floods occurring in these streams are discharged from the canal through spillways constructed at suitable intervals.
 
The E. M.Y.E canal will be utilized for he following restricted purpose when the scheme is fully developed: irrigation of system G, And augmentation of the Minneriya tank from the Kalu Ganga reservoir, Amban Ganga, and the canal catchment itself. In the reach from Minneriya to Kantalai, the canal will serve as a waterway for the spill flood discharges from Minneriya to Kantalai, and, by suitable connections, from Kaudulla.
 
However, in the first phase of development – that is, before water is diverted to the N.C.P – the Elahera canal will also be used to augment the tanks in system D – 1 from the Amban Ganga. For this purpose, a minor improvement is proposed in the head sluice and the initial section of the canal (from mile 0 to mile 6) : the increasing of its conveyance capacity to 1.500 cusecs. This improvement involves the construction of an additional head regulator to discharge 500 cusecs, and increase in height of the lining of the canal, and the raising of the crest of its spillway by 2 – 3 feet. Apart from this only local improvements of the canal bunds and construction of suitable approaches at entrances of the     cross – drainage streams need to be done.
 
  1. PolgollaKala Oya (P.K) Canal
 
The alternatives considered for the canal are:
(i)                  diversion at Diggala site and total length of the trace 19.07 miles;
(ii)                diversion at Bowatenne site and total length of the trace 9.25 miles;
The first alternative requires an open - out lined canal which, through difficult topographic and geological conditions, will need, in addition, four short tunnels and 10 major structures (6 syphones, 1 energy dissipater, 2 regulators at the spillways, and I fall structures).
 
The total cost is estimated at Rs. 97.4 million (pre – devaluation), a good part of excavation cost being for machine work. When estimated on the basis of using manual work as far as possible, the cost is Rs. 84 million (pre – devaluation), Rs. 57.0 million of which is local expenditure, the balance being required in foreign exchange. Annual operation an maintenance expenditure comes to Rs. 840,000 (pre – devaluation)
 
The chief advantages of the first alternative is that it can be implemented with a minimum foreign exchange and be carried out simultaneously with the construction of Polgolla, thus permitting the operation of the required part of system G as early as in the fourth and fifth year after the commencement of the project.
 
The disadvantages are the high capital and operation costs of maintaining the canal to withstand floods and landslides.
 
In the second alternative, the canal runs for the greater part of its length through a tunnel 4.25 miles long which crosses the water divide between the   catchments of the Amban Ganga and Kala Oya. There after it coincides with the tail reach of the first alternative.
 
The cost, all apportioned for irrigation purpose, is estimated at Rs. 56.3 million (pre-devaluation)
 
When the possibility of developing hydropower in two directions from Bowatenna (toward Moragahakanda and toward Dambulu Oya) was considered, positive advantages were found in   raising the height of Bowatenne dam by 20 feet thus creating a reserve storage of 20,00 acre – feet and giving greater assurance of water to systems H, D and 0. This also permits the installation of a tur­bine of 3.7 megawatts capacity (of which 2.2 megawatts is firm power) at the Dambulu Oya and the construction of a hydro-electric station at the Amban Ganga end with firm power capacity of 15.4 megawatts.
 
The total cost of the second alternative in this arrangement is estimated at Rs. 62.5 million (pre-devaluation), excluding the cost of the Amban Ganga tunnel and power plant. Of this sum, Rs. 32.5 million are required in local currency, and the balance has to be obtained from foreign sources. Annual operation and maintenance costs will amount to Rs. 400,000. With the increased height of Bowatenne bariage, the second alternative is cheaper than the first by Rs.. 21.5 million in capital expenditure and by Rs. 440,000 (pre-devaluation) in annual operation and maintenance costs. The foreign exchange requirement in the second alternative is, however, greater (by the equivalent of Rs. 3.0 million). This amount could be saved if the tunnels were constructed after completion of the Polgolla tunnel, the same machinery and equipment being used. But then the required part of system 1-I could be put into operation only after a delay of two years and an income of Rs. 20 million from this area would have to be foregone.
 
The total cost of the second alternative, if the height of Bowatenne dam is raised and the tunnel as constructed after completion of the Polgolla tunnel, can thus be considered as Rs. 62.5 million+ Rs. 20 million. This cost of Rs. 82.5 million is very close to the Rs. 84 million of the first alternatives. Preference was given to the second alternative, since its operation cost is less than half that of the first alternative and since income losses from delay in bringing into operation the required part of system H are theoretical.
 
The Polgolla-Kala Oya canal, as adopted to this second alternative, will be as follows
 
The dam at Bowatenne will serve as a bifurcation structure. It will be 107 feet high and 804) feet long along the crest and designed to cope with a flood discharge of up to 124,500 cusecs (occurr­ence of once in 1,000 years).
 
The tunnel intake towards the Dambulu Oya will be located in the bay of the proposed reser­voir. A pressure tunnel, 16 feet in diameter and 21,500 feet long, will be designed to convey a maxi­mum discharge of 750 cusecs. A small hydro-electric station will be installed at its outlet to produce 16 million kWh firm energy annually.
 
The open-cut canal beyond the station will be 4.89 miles long and have concrete lining in a part of the first mile.
A 266 feet long syphon, a drop structure, and a regulator at the spill to the Dambulu Oya will be provided en route.
 
Geologic conditions at the sites for construction of the barrage and the tunnel are favourable for a darn) with adequate grouting. The foundation consists of gneisses and crystalline limestone at 5-20 feet below the loosely fragmented and weathered formation.
 
The tunnel trace will be driven at a depth of 100-600 feet in practically fresh metamorphic rocks (gneisses, granulites, quartzites, and crystalline limestone) in which layers occur at an angle of 200 -600  to the tunnel axis. It is only at the tunnel inlet and outlet that loosely fragmented and weathered material will be encountered.
 
The total post-devaluation cost of Bowatenne amicus and the P. K. canal is Rs. 73,050,000, of which Rs. 35,940,000 are required in foreign exchange, and Rs. 37,110,000 locally.
 
6.   Irrigation Systems D-1 and C
General Conditions of irrigation
 
(a) Available land resources
 
Systems D-l and C, which cover a total area of 100,500 net acres, are adjacent, and are supplied with water from the same trunk canal, the Elahera-Minneriya-Kantalai-Yoda Ela.
 
System G is irrigated directly from the trunk canal, and system D-l is irrigated from the Minne­riya, Kaudulla, and Kautalai tanks. Available land resources include the following areas.
 
System G                                                          4,900  acres of existing paddy fields
                                                                        7,440  acres of undeveloped lands
 

Total                                                                 12,340  acres
 

System D-1                                                       43,400 acres of existing paddy fields
                                                                          7,700 acres of existing sugar-cane plantation
                                                                        37,060 acres of undeveloped lands
 

Total                                                                 88,160 acres
 

Total of  D-1 and G                                           100,500 acres

                                                           
Natural conditions and homogeneous in the two systems and they can be considered together.
 
(b) Effective precipitation and irrigation duties
 
The effective precipitation was estimated for three critical years, 1947148, 1956/57 and 1958/59, when there was respectively 81 percent, 75 percent, and 76 percent frequency of occurrence. The average effective precipitation during these three years is tabulated below.
 
 
TABLE 3
 
Average Effective Precipitation for Three Critical Years, 1947/48, 1956/59 in
Systems D-1 and G.
 

                                                                                        Average                                Percentage of Crop
                         Crops                                                Effective precipitation                 requirements
                                                                                 -----------------------------                  -------------------------
                                                                                 Maha         YaIa Annual               Maha                  Yala
                                                                                

feet
                     Paddy            ..                                                                 ..                                        1.98           0.64       2.62                    72                            20
                     Dry crops ..                                                                                ..                                        1.52           0.53       2.05             84 71                      30 24
 

The Table above shows the effective precipitation in both seasons to be insufficient for the growth of paddy and the majority of dry crops. In Maha, only some types of dry crops get almost all the moisture they need, provided the distribution of effective precipitation during the period is favourable. Consequently, this region requires guaranteed year-round irrigation.
 
Average gross irrigation duties for the main types of cropping pattern are as follows :-
 
                                                                                                TABLE 4
 
Average Gross irrigation Duties for Main Crops
 

                Type of cropping pattern                                             Maha                      YaIa                    Annual
 

                                    (0                                                                        (2)                        (3)                           (4)

                Paddy . .                                                                                                   -.                                                                       ..                                                       3.4                          5.1                           8.5
                Mixed (Paddy and subsidiary        crops)                  2.8                          2.7                          5.5
               
Sugar-cane                          ..
                                                                        ..                                                       2.6                          4.6                           7.2
                High value crops                ..
                                                                        ..                                                       1.7                          2.8                           4.5
                                                                                                                                        
 
(c) Relief and soils
 
The relief of the region as a whole can be rated as suitable for gravity irrigation. System C and the upper part of system 0-I have slightly undulating relief with differences in elevation of 20-30 feet and slopes of 2 - 3 degrees. The lower part of system D-1, bordering upon the Mahaweli Delta. is flatter with relatively moderate slopes of I - 1.5 degrees.
 
The soil cover consists of four major varieties, Reddish Brown Earth (RBE), which has good drainage conditions and forms 40 percent of the total useful area; reddish brown earth (RBE) imper­fectly drained (10 percent); Low Humic Gley soils (LHG) and Alluvial soils (Al), poorly drained (CO percent). The Reddish Brown Earth (RBE) is the most fertile, and is capable of producing all o~ Le high value dry crops and sugar-cane. The Red Brown Earth (RBE) with imperfect drainage conditions is suitable for rice and for several other dry crops cultivated during Yala. I he gley soils can be used for paddy rotations.
 
(d) Reclamation of low-lying areas from periodical floods
 
The reclamation of lands affected by the periodic inundating of the alluvial plains and low-lying areas of system D-l must be considered.
 
The settlement of new territory in system 0-1 required a new, though not very large. infra­structure.
 
Existing irrigation
 
The existing irrigated lands of system 0 stretch along the Elahera trunk canal and merge with the area proposed for new development, forming one block.
 
In system 0-I, the existing irrigated lands are under command of the four tanks augmented by the Elahera canal (Giritale, Minneriya, Kaudulla, and Kantalai see general layout plan, Drawing No. 1). Information on areas irrigated under these tanks is given in Table 5.
TABLE 5
 
Characteristics of Existing Irrigation Tanks of System DI
 

Name of Tank                                                                                                                                          Irrigated Area
                                                                      Catchment       Average     Yield     Active        -----------------------------  
                                                                  Area               yield     P-75%    storage       Paddy      Sugar     Total
                                                                     cane

               (1)                                                   Sq.                         (3)              (4)             (5)              (6)              (7)              (8)
                                                                               mile              ac/ft          (thousands)                            acres
Giritale                          ..                                                                  ..                                                       9                     5                3             19              4,400                                                             4,400
Minneriya ..                                                                                                                          ..                                                   93                   50              27           109            14,300                                                          14,300
Kaudulla ..                                                                                                                                
..                                                   32                   32.5           18             94            10,200                                                          10,200
Kantalai and Vendarasan                ..
                                                   81                   81              46.4        130            14,500        7,700         22,200
 

                  Total           ..                                                                  ..                                                        215             171.5               94.4 352               43,400       7,700       51,100
 

All the existing irrigation systems were reconstructed in the last 15—20 years, the most recent being the Kaudulla and Kantalai systems. The common disadvantages of the existing systems are insufficiency of the irrigation network, unsatisfactory drainage conditions, and the very widely spaced system of field canals.
 
Watering of paddy is maintained by transference from one ‘liyadda’ or small paddy tract to another. Water use is not economical and considerable losses occur.
 
Statistics taken over the last 14 years reveal that the irrigated area has been adequately supplied with water only during Maha season. In Yala, watering was-provided for the whole area under irri­gation in seven years only ; one dry year had almost no irrigation during both seasons, and in the remaining six years water was supplied for only 80— 90 percent of the area during Yala.
 
In order to determine the extent of assured irrigation in the existing irrigation systems, a study was made of the present scheme of water supply in a critical year with 75 percent frequency of occurr­ence. A comparison between the estimated and statistical data is shown in Table 6.
 
TABLE 6
 
Present Irrigation Intensity of (lie Existing Areas in System D
 

                                                                             Area with              Crop acreage                     Crop                   Coefficient
                    Data                                                  irrigation               ------------------                  acreage                  of
                                                                              network                 Maha        Yala                 total                     intensity
 

Acres ( thousands)
Estimated for the year of
75 percent frequency                     ..                                                                   56.0                  56.0          27.0                  83.0                        1.48
 
Statistical                  ..                                                                       ..                                                                   56.0                  56.0          42.6                  98.6                        1.78
 

Thus it can be seen that the irrigated area, according to the statistical data, exceeds that esti­mated in the operation study by 15,600 crop acres. Obviously, its frequency of irrigation is less than 75 percent. in the agro-economic estimates, to be on the safe side, the greater extent of the irrigated area was adopted; this gives a somewhat lower ‘value added’ after the existing irrigation systems are completely satisfied with water.
 
The operation study data were used to determine the equivalency coefficient (ratio) of the additional water supply for the existing irrigated lands to the requirements of the areas new to irriga­tion. In this case, the partial augmentation of the 56,000 acres of existing systems will permit the sure irrigation of an additional 29,000 acres in Yala, which is equivalent to the year-round irrigation of new lands amounting to 14,500 acres (29,000+2). In other words, the augmentation of the 56,003 acres of existing lands is equivalent to 14,500 acres of new irrigation; the equivalency coefficient is around 14,500: 56,000.
 
The planned augmentation of the Amban Ganga will improve the assured water supply to the irrigation systems up to 85 percent.
 
With the aim of having a properly arranged irrigation network and a more productive use of irrigated lands, it is proposed to improve the existing systems by the following means
 
(i)    Modernisation of the head sluices and regulators on the main and branch canals, including the installation of water measuring devices, at a cost of Rs. 9.7 million.
 
(ii)    Reconstruction of the main drainage lines, by deepening and widening their channels and construction of embankments in the lower reaches of the streams, at a cost of Rs. 14.1 million.
 
(iii)   Intensification of the field irrigation and drainage network so that the space between the feeders is not more than 600 feet, with adequate improvements to field canals, at a cost of Rs. 11.6 million.
 
The total cost of improvements to the existing amounts to Rs. 35.6 million.
 
New Irrigation
 
(a)    System D-1
 
The newly irrigated lands of system fl-I will be under the command of the Kaudulla and Kantalai tanks. To create a consolidated system of water supply, it is proposed to connect these tanks by a link canal, which will simultaneously irrigate lands en route from the Kaudulla tank. In the third
 
phase of development, when the Kaudulla tank will be augmented from the Mahaweli Ganga through the L. B. transbain canal, the above link canal will permit augmentation of the Kantalai tank with waters from the Nlahaweli.
 
The lands to be irrigated under the Kaudulla tank cover 30,530 acres, generally isolated from the existing irrigation system. New conveyance canals 28 miles in length will be constructed here to cater for blocks of 5,000 or more acres.
 
The lands proposed for irrigation under the Kantalai tank (6,480 acres) are under command of existing canals in the adjacent irrigation systems. This permits the use of part of these conveyance canals for irrigation of the new lands.
 
A narrow strip of land covering 9,100 acres of system A and lying along the eastern boundary of system 0-1 is proposed for irrigation, also from the Kantalai tank., in Project 3 of the first phase. This strip shares a common water conveyance network with system 0-1, which lies at higher elevations.
 
To summarise, the irrigation of all lands under command of the Kantalai tank, a total of 15,580 acres (6,480 + 9,100), requires 16.8 miles of water conveyance canals, of which & miles involve the construction of existing canals, and 8.8 miles must be of new construction.
Two methods of irrigation have been proposed furrow irrigation for 18,380 acres, and border irrigation for 18,680 acres.
 
To control water usage, the irrigation network will be equipped with accurate automatic water measuring devices at the head of blocks of 200— 250 acres. Within these blocks the discharge will be measured by farmers through calibrated outlets or portable syphons.
 
The main drainage lines of system D-l, will be deepened and widened as necessary in the up­stream reaches and trained in the lower reaches. Drainage channels serving blocks of 5,000 acres in the upper part of the system are generally led to the existing streams, where usually no improvements will be required. In the lower part of the system, where the conveyance capacity of the natural streams is insufficient, trenching of artificial drainage lines is proposed.
 
(b) System G
 
The new irrigated lands in system G (7,440 acres) are adjacent to the existing irrigation systems and will use the same network of distribution and drainage. The entire area in this system will be under border irrigation.
 
(0 Cost of new irrigation in systems D-l and G
 
The cost of the main irrigation and drainage system was estimated for each canal. The cost of the irrigation and drainage network, and of levelling and jungle clearing, was determined by apply­ing the unit cost of these works derived from the standard plot. The total cost is estimated to be
Rs. 1 10,590,000.
 
The total estimated cost, comprising improvement of the existing schemes, construction of new systems arid land development, is Rs. 146.19 million. Operation and maintenance costs are estimated at Rs. 3.3 million per year.
 
7.       Irrigation System H            
Conditions of Irrigation
 
System 1-1 is located in the Kala Oya basin. Its total net area is 103,100 acres, of which 46,200 acres are already irrigated and 56,900 acres are proposed for new irrigation.
 
The existing systems are fed by seven tanks, the more important of which are Kandalama, Kalawewa, LJsgala and Rajangana; the undeveloped lands are in the zone of command of the Kanda­lama and Kalawewa tanks, for which water will be supplied from the Mahaweli Ganga through the P. K. canal. All tanks located below Kandalama are connected by natural streams or canals.
 
The climate of the Kala Ova basin is slightly more arid than that of the Mahaweli Ganga basin. Cultivation of rice and dry crops under rainfed conditions is possible only in Maha, in the wet sears. The distribution of effective precipitation is critical years and the corresponding average values of irrigation duties; are given in Table 7.
 
TABLE 7
Effective Precipitation for Critical years and water Duties in System H

                                                                                    Percentage of
     Crops                                  Maha          Yala       Annual           Consumptive  use                   Irrigation duties
                                                                                                           ----------------------                      ----------------------------
                                                                                                           Maha             Yala                  Maha                  vala
 

                                                                        Feet                                                                                           Fed
     Paddy                                   1.45           1.00           2.45              53                  32                         3.5                      5
   
Dry crops                             1.15           0.83           1.98          62 - 46           41 - 28                  0.8 - 2.2             2.2 -2.8
 
 

Soil conditions of the area are favourable for growing value crops. Fertile and well drained Reddish brown Earth (RBE) soils prevail in 66 percent of the irrigable area. The Reddish Brown Earth (RBE) with imperfect external drainage occurs on 8 percent of the lands, and the gley soils (suitable for rice) and alluvial soils cover the remaining 26 percent.
 
The relief of the water divides is slightly undulating. with moderate slopes varying front I  3 de2rees the terrain is flatter in the river valleys, where slopes are smoother.
 
The greater part of this area has favourable conditions for land reclamation, there being no swamps or danger of salinisation. Only the river valleys are subject to periodic flooding in brief spells: hence, sonic flood protection is necessary.
 
Existing irrigation
 
Two types of irrigation systems exist in the Kala Oya basin: major schemes involving engineering works and minor village schemes.
 
Major irrigation schemes are similar to those described earlier under, the Kaudulla and Kantalai tanks. The chief defects of these systems are the lack of proper devices to control the water issues, insufficiency of the field irrigation network, and inadequacy of drainage. Most of the irrigated lands are at present tinder paddy cultivation, the few exceptions being under mixed rotation of crops. Dis­tribution of the irrigated areas under the existing feeder tanks is given in Table 8.
 
 
TABLE 8
 
Characteristics of Existing Irrigation Tanks in System H
 

                                                                                          Averace        Active           Active              Existing Acreage
Name of Work                                      Catchnient         yield             P—75t,          Storage -                          ------------------------------------------------------_
                                                                                                                                                                                                                    Area              1,000             1,000           1.000            Major           Minor
                                                                                                                                                             Schemes       Schemes

 
                                                                       Sq. miles                         acre feel                              acres
     Kandalama                 ..                                                            ..                                    38                   26                   12             25.6          4,000                       3,280
     Kalawewa..                                                                                                                                                      260                 180                  82              72.7           13.020                    6,900
Usgala
    Sivambalagamuwa                           ..                                 71                   49                  23             20.7             1.500                         -
    Rajangana                 ..                                                                      ..                           177                 123                  54             76.5           17.500                         -
 

                                                                                                                                                     36,020         +          10,180
                                                                                                                                                     Total            =        46.200
 
 

There is no assurance of continuous water supply to the above areas and, according to statistics collected over 14 years, an average of only 30 percent of lands irrigated in Maha were irrigated during Yala season. In some years the water supply was even less, and in one of the 14 years there was no irrigation at all in Yala.
 
The adequacy of water supply to the existing areas in system U was measured from estimates similar to those made for systems D-l and 0. The results of the processed statistical data and the operation estimates for the critical year of 75 percent frequency of recurrence are tabulated in Table 9.
 
TABLE 9
Present irrigation intensity   of the Existing Area in System H (1,000 acres)
 

                                                     Area with                                    Total               Coefficient of
        Data                                      irrigation        Maha      YaIa          crop                    intensity
                                                      network                                      average          
    Estimated           ..                       46.2              42.2       22.4          64.6                     1.53
    Statistical           . .                      46.2              42.2       19.0          61.2                     1.45
 

Although the areas of crop acreage obtained by different methods are closely similar, a discrepancy in the intensity coefficients is seen. However, since the estimation of ‘value added’ is based on the statistically determined total crop-acreage, the difference in the intensity coefficients does not affect the economic estimate. The equivalency coefficient’ of the existing irrigated lands is around 0.3 as in system D-I and 0.
 
The same basis is used for the proposed improvement to the engineering systems as for the existing schemes in system D-l.
 
Village irrigation schemes are dependent on small tanks which provide for watering of paddy during Maha season only. These schemes vary in size from 5 to 50 acres and total 10,180 acres. The tanks are created by low bunds (sometimes 3-4 feet high) across shallow valleys of small streams. The water surface area of the tanks sometimes exceeds the area; irrigated. Spilling of flood waters is normally through shallow excavations, the head sluices are primitive and a concentrated irrigation network is lacking. in several instances there are cascades of bunds barring water flow along the natural streams: this leads to over-moistening of the whole stream valley.
 
It is proposed to reconstruct the village irrigation works which will be absorbed in the new irrigation systems and to use some of the existing tanks as water regulators to irrigate the paddy fields lying below them. Where the village irrigation scheme is excluded from the new systems, or where its area is not convenient for expansion, some improvement to the irrigation and drainage network, as well as augmentation with return waters available from the new irrigation, is contemplated.
 
The cost of the improvement and reconstruction of the existing irrigation schemes under system H is estimated at Its. 27,440.000.
New Irrigation
 
The greater part (85 percent) of the new irrigation area, covering 48,205 acres, is located in the zone under command of the Kalawewa tank; only 8,695 acres will be irrigated from the Kandalama tank.
 
For reasons explained in the next section (Water Supply to the Irrigation System), only 31.300 acres, or about 70 percent of the 48,205 acres of new irrigated area commanded by Kalawewa Tank in system H, will form part of Project I. The balance of 16,900 acres will form part of Project 3.
 
I,   Coefficient expressing the relationship between the water consumption of an already irrigated area and an area proposed for irrigation.
 
The allocation of the new irrigated area for Kite whole system, to projects and by method of irrigation, is shown in Table 10. The remark which follows, except the details of costs, apply to system H as a whole.
 
TABLE 10
Allocation of New Irrigation Area in system H
 

                    Area in 1,000                               Total                Project I            Project 2
 

                       Existing ..                                46.2                    46.2
                       New ..                                    56.9            (31   300—8  695)        16.9
                           Border irrigation                   19.3                     13.7                     5.6
                           Furrow irrigation                  36.5                     25.6                    10.9
                           Sprinkler irrigation                  1.1                       0.7                     0.4
 

            The newly developed lands of various systems under Kalawewa tank will exceed by almost 2.5 times its existing irrigated area, thus calling for considerably greater use of the local water yield. Under present conditions, the tank fills up as a rule in the middle of the Maha season; after which, until the beginning of Yala, it is generally full and spills off the extra inflow. With the increase of the irrigated area, the spilling off can be reduced to a minimum by gradual controlled filling of the tank with water released from the Mahaweli. Thus the available active storage of Kalawewa, when augmented from the Mahaweli Ganga, will be sufficient to irrigate the proposed area. It should be emphasized, however, that an increase in active capacity of Kalawewa is desirable, as this would appreciably improve water distribution.
 
The main canals in system H were designed to obtain maximum use of the existing channels by including the existing left and right-bank channels of the Kandalama tank, and the right-bank channel of the Kalawewa tank. These channels will be reconstructed suitably, a new trace being proposed for the left-hank channel of Kalawewa. The total length of the main canals and their branches is about 96 miles.
 
The main drainage line will be the Kala Oya itself Its conveyance capacity and the level regime satisfy the requirements of the water intake for the drainage and spill flows. However, during floods. the river overflows its banks and inundates a part of the developed area. For protection, the lower areas will have embankments and the river channel discharge capacity will be improved by excavation. Branch drainage lines will follow the natural streams their channels will be deepened and widened wherever necessary and the reaches at the confluence will be trained. The total length of the main drainage lines and their branches is about 80 miles.
 
The cost of irrigation in the 70 percent of new land for irrigation in system H which is being included in Project I is estimated at Rs.90,210,000. Since, as reported above, the cost of improving and reconstructing the existing irrigated land of the system is Rs.27,440,000, the total cost of system I-I in Project I is Its. 117,650,000. The operation and maintenance expenditure is Its. 2,600,000.
 
8.    Water Supply to the Irrigation Systems
 
The principle of water supply to the irrigation systems included in Project I consists of regulating the diverted water of the Mahaweli Ganga into tanks of the irrigation systems and issuing it to the irrigation network as required. The tanks can provide seasonal regulation for the yield from both the local catchments and the augmenting system but effective use becomes possible only under a certain regime of water supply. Two main rules of water operation must be followed
 
(i) In Maha, full discharge is to be conveyed until the tanks are filled to NWSEL,1 or 3-5 feet beIow NWSE L thereafter, the discharge conveyed from Polgolla should not exceed current water consumption, with care being taken to reduce conveyance to nil if the tanks spill.
 
1.    NWSEL = Normal
Water Surface Elevation.
 
(ii) At the beginning of Yala, the augmentation is to be carried out by maximum flows in order to fill the tanks to NWSEL before peak use, which occurs in July.
 
Operational studies performed in accordance with these rules over a 20-year period, considering 5-day discharges at Polgolla and daily discharges at Elahera, showed that the augmentation from the Mahaweli needs quite a regular regime, which can he maintained in practice.
 
These operational studies, performed for the whole area tinder system H. revealed that there was a deficit in water supply for 7 years out of 20 in the Kalawewa tank and that the assurance of irrigation of lands under its command did not exceed 65 percent, which is lower than the adopted rate. After reducing the new area wider command of the tank from 48,200 to 31,300 acres (i. e. by 16,900 acres, or about 30 percent of the area in system H), the assurance of irrigation reaches 85 percent which is the standard for all lands under Project 1.
 
The regime of water supply was determined by the design rates of water consumption and was later checked at the higher duties for existing paddy and sugar cane cultivation. The increase in duties affected water supply to the lands under command of the Kalawewa tank only; for other tanks in system H, D-l and G. this increase can generally be met, without adversely affecting irrigation of the new lands.
 
Results of the water control estimate for the Kalawewa tank are tabulated below
 
TABLE II
 
Kalawewa — Water Control Estimate
 

Years of deficit
in the 20 years           45/45    45/46     47/48   49/50     52/53      55/56     58/59       Notes
series

 

Amount of deli-                                                                                                    Water consump­-
cit in the critical                                                                                                    tion Pot 48,200
months (June,                                                                                                       acres: June 43,800
July) 100 ac. ft.                                                                                                     ac.ft. July,
for area of 48,200                                                                                                 33,800 ac.ft.
acres.                     12.7        9.2        31.5    15.7         42.0       22.7          8.0
 

Area assured                                                                                                        Water consump
with irrigation                                                                                                        tion for 31.300
(% of given area)    62          73          25          54            0           32             76      acres: June 28,000
                                                                                                                            ac.
ft.
July
21.800
                                                                                                                            ac. ft.


Amount of defl-                                                                                                    Increase in duty
cit for reduced                                                                                                      for existing pad
area of 31,300                                                                                                       over design duty
acres.
                                         17.0         3.7         27.0        10.7               0.1 acre feet per
                                                                                                                            acre in critical
                                                                                                                            month.
 
 

It can be seen from Table 11 that with the reduction of the area to 31,300 acres, the deficit occurs in four years out of 20 ; in one year of the four the deficit is only 16.5 percent of the consumptive use and this can practically be ignored. It may be considered that the assured water supplies to the area of 31,300 acres will be approximately 85 percent. The reduction of the area will also offset the insecurity of considerable deficits in the three consecutive years, occurring in the case of the full irri­gated area tinder the Kalawewa tank.
 
The above considerations dictated the deferment of the development of 16,900 acres within the new lands of system H until the third phase of development, by which time an additional water source will give 100 percent assurance of water issues to the entire area in this system.
 
9.   Settlement and Agricultural Use of Lands
 
Development of the newly irrigated lands is based on the settlement of farmers transferred from overpopulated regions of the country. The main contingent of the relocated population will be farm­ers on small holdings (5 acres) whose production will be based on the labour output of the family, using animals and small machines to assist with the most laborious tasks. A smaller number of farmers is proposed for medium-sized farms (I 5 acres) on which specialized cultivation of high value crops, with a higher level of mechanisation and hired labour, is envisaged. Urge plantations (200 acres) are proposed for growing cotton and sugar-cane; they will be highly mechanised.
 
The data of farm organisation is summarized in Table 12.
 
TABLE 12
Farm Organisation
 

                                                                  Medium                    Large
    Systems                  Small farms              size farms               Plantations                    Total
 

                            number    area        number    area        number       area        number       area
                                            acres                      acres                      acres                       acres
                                           (l,000s)                    (l,000s)                    (l,000s)                     (l,000s)
 
D and G                6,520        32.6          460          6.9                     5.0            6,980        44.5
H                          6.059        30.3          368          5.5           21          4.2            6,448        40.0
 

    Total                12,579        62.9          828         12.5           21          9.2          13,428        84.5
 
 

Of the total number of 12,579 small farms, 9,615 will be established by new settlers, each farm representing a family. The other 2.964 farms will be provided by enlarging” the present holdings. On the medium-sized farms and large plantations, in addition to the farmers, 1,832 families of agricultural labourers will be settled.
 
To create proper conditions for providing community services, the settlements will be set u p as villages containing 400 — 500 families ; a consolidated system of water supply and electrification, administrative services, hospitals, schools, and other public Institutions will be located in ‘townships’.
 
To render services in the field of administration and management, medicine, education. etc., 2,100 families of service personnel will be required in the townships and villages. There will be 26 new villages, and 8 new townships, and the total number of families to be resettled is 14,396.
 
The total costs (‘post-devaluation’ rates) of settlements for the development area are given in Table 13.
 
Agricultural use of the irrigated lands was designed by applying the following cropping patterns.
 
Paddy (paddy + paddy + legume) (1)
 
Mixed rotation (paddy + high value crops + legume) (2)
 
High value crop rotation (cotton, chillies, groundnut, vegetables, etc.) (3)
 
Sugar-cane (5)
 
It is proposed that the existing paddy lands be used for paddy rotation, while other lands presently irrigated will preserve their existing pattern of crops.
 
The estimated yield of the crops was based on the average level of farming practice which can’ he achieved through moderate improvements to the existing practice. Below are given the estimated yields of the main crops per acre:
Paddy (Maha and Yala) – 56 and 61 bushels.
Cotton (one season) – 10 cwt.
Groundnuts (one season) – 12 cwt
Maize (one season) – 20 cwt
Onions (one season) – 80 – 90 cwt.
Sugar cane (one serason) – 25 tons
 
Distribution of the irrigated lands by cropping pattern and the expected benefits are shown in Table 14.
 
TABLE 13
Project 1: Land Settlement Costs (post – devaluation rates)
 

                                                                                    System D G                              System H

                                                Foreign Project             Net allo-           Project             Net allo-
                                                Exchange          Proper              cation to           Proper              cation to
                                                                                                Project                                     Project

                                                                        Rs. (100s)        Rs. (100s)        Rs. (100s)        Rs. (100s)
 
  1. Health               ..              30%               1,800               2,450                  800               1,080
  2. Education          ..                                            -               7,263                       -               3,676
  3. Water Supply    ..              40%               9,500               1,588               5,300                  887
  4. Electricity          ..                                            -               6,930                       -               3,867
  5. Settlement Roads 10%     1,600                  248                  900                  131
  6. Farmers Cottages              10%             23,700                       -             11,100                       -
  7. Extension services             60%               4,500                       -               3,600                       -
  8. Irrigation Department         10%               1,300                       -               1,500                       -
  9. Paddy stores                                                   -               3,266                       -               1,707
  10. Farm working capital
    1. New acreas           25%             17,800                       -             20,000                       -
    2. Existing area        100%               5,300                       -               3,300                       -
  11. Experimental Farm            60%                  200                       -                  800                       -
  12. Postal services                                                -                  819                       -                  492
  13. Police                                                             -                  428                       -                  257
  14. Veterinary services                                          -                  185                       -                    11
  15. Civic center                                                     -                  625                       -                  345
  16. Land Com. Department     10%               1,100                       -                  600                       -
  17. Social services                   10%                  100                       -                  100                       -
  1. Co – op                                                          -                  625                       -                  345

    Totals by system                        66,900             24,427             48,000             12,898

Total Project proper                                                                114,900

 
 

Apart frown these costs, which are allocated to the project proper, certain additional costs which cannot be directly allocated 10 the project will be incurred. These will include a part of the cost of land settlement. Transmission lines, and also a part of overhead charges; all amounting to Rs. 46.9 million.
 
The current expenditure required to operate the hydro-electric station and the irrigation systems, as well as service to be rendered for the farmers, is estimated at Rs. 10 million (operation and mainte­nance of the irrigation systems, Rs. 7.3 million: operation and maintenance of the H ES. Rs. 0.4 million; on extension services. Rs. 2.3 million).
 
Based on the ‘value added’ from production and benefits with minor improvements in present agricultural methods, and considering the duration of construction and development, the following ‘post-devaluation’ indexes of economic efficiency were obtained
 
Capital cost—Net benefit ratio 4.4 : 1 (market prices)
 
Internal rate of return       17 percent at market prices
                                                     21 percent at accounting prices
 
As has already been pointed out, the release of water from Bowatenne toward N4oragahakanda can be used for power generation. The hydro-electric station at Bowatenne is designed to have an installed capacity of 40 megawatts and firm power production of 135 million kWh. The cost of the conveyance and hydropower plant is estimated at Rs. 42 million.
 
The value added’ from the power at bus bars of the station provides, according to the estima­tion, an internal rate of return of 15 percent.
 
Bowatenne hydra-electric station may be considered as quite independent; in order that more electricity can be provided when it is required (which depends on the actual power consumption in the next five years), it is expedient to construct this station in the first phase simultaneously with the P.K canal.