SATGE I — PROJECT DESCRIPTION

 

The engineering works comprising the Mahaweli Ganga Development, to be constructed under Stage I, include the Polgolla complex, the Bowatenna complex, the Sudu Ganga training works and the remodelling of the Elahera weir and the Elahera-Minneri-Kantalai canal. When these works are completed in 1975-76, additional water from the Mahaweli Ganga and the Amban Ganga could be made available to make up the deficiency in the water supply to existing irrigated lands of 52,400 ac. in areas H and IH including Huruluwewa and 74,185 ac. in areas Dl, D2 and 0. The works to be constructed in Stage I are designed to meet the ultimate water requirements of 217,585 ac. of existing and new lands in areas H and IH (123,400 ac.) and Dl and G1(94,185 ac.) which would be developed in Stages II and III respectively.

 

In addition to the engineering works, Stage I includes detailed investigations of existing and new lands in areas H and IH to be developed in Stage II which, inter-alia, including preparation of the feasi­bility report, detailed cost estimates, aerial survey, land classification and development, irrigation and drainage water cropping patterns and water requirements, settlement of farmers and agriculture exten­sion services. Drainage and land levelling equipment is provided for on-farm development of 7,000 ac. of sugarcane in area Dl.

 

Polgolla Complex

 

The Polgolla complex consists of a low diversion dam across the Mahaweli Ganga about a mile downstream of Kandy city, a 5-mile long diversion tunnel to divert the Mahaweli flows to the Dhun Oya, thence into the Sudu Ganga, a tributary of the Amban Ganga, a 40 MW hydro-electric plant at the end of the tunnel with a by-pass outlet for irrigation releases and a tail-race canal outfalling into the Dhun Oya, a tributary of the Sudu Oanga.

 

The diversion dam would be a concrete ogee structure, 565 feet long at crest and 55 feet high above foundation, with ten hook type spillway gates, 21 feet high and 40 feet wide, and a 24 feet wide roadway on the crest. The spillway would be capable of passing a discharge of 210,000 cusecs, which corresponds to a flood of 100 year frequency, without causing any significant damage to developments upstream and without affecting the railway bridge located about 6,100 feet upstream of the Polgolla site. The dam would be operated to provide a minimum continuous release of 150 cusecs downstream for sanitation, wild life and domestic use and to head up water up to the maximum operat­ ing pool level at elevation 1,446 feet when the maximum head across the dam would be 23 feet. The minimum operating pool level would be at elevation 1,438 feet which would provide a regulating storage of 2,000 ac. ft. The geology of the site is favourable for constructing a low dam. The site had been selected after examining other alternatives both upstream and downstream, the main consideration being the suitability of the tunnel intake and not the geology. Rock outcrops are exposed at a few points both upstream and downstream of the site. The rocks are mostly quartzo- feldspathic-biotitic gneisses having almost vertical dips. Seven holes with an aggregate length of 312 feet have been drilled along the axis of the dam. The core data revealed that weathering was deeper, particularly on the right bank, but sound rock was available at a maximum depth of 20 feet to adequately support the structure. The foundations would require grouting and an upstream grout curtain would be cons­tructed to avoid uplift pressures under the downstream floor.

 

The diversion tunnel would be 26,450 feet long with a horse-shoe section 19 ft. bin, in diameter, capable of diverting 2,500 cusecs of the Mahaweli flows into the Amban Ganga through the Dhun Oya and Sudu Ganga. It would be a pressure tunnel and would be lined about 30% of its length~ The tunnel alignment has been selected after considering several alternatives. Although 28 bore~ holes with an aggregate length of 3,709 feet have been drilled in the region for examining alternative alignments, the geological data along the final alignment is based on 5 drilled holes only with a total length of about 1,000 feet. The rocks along the tunnel trace consist mainly of gneisses with inter-beds of quartzite’s and granulites except in the tail-end where hard crystalline limestones and calc gneisses were found. Several closed faults and shear zones traverse the tunnel area and are represented by long and narrow drainage valleys at the ground surface between mountain ridges. At these sections, problems of fractured rocks aiid seepage water are likely to be encountered during construction. Sev­eral geologists visited the site from time to time during 1959-68 and expressed favourable views on the feasibility of the tunnel. Experience on the construction of the Maskeliya tunnel, which is also 5 miles long and passes through similar geology, supports the conclusion that no unsurmountable problems would be expected during the construction of the Polgolla tunnel. Nevertheless the data of only 5 bore holes along a 5-mile long tunnel does not provide sufficient information to international contrac­tors to prepare accurate and competitive bids and it would be prudent to carry qut additional drilling before the tender documents are issued. The Irrigation Department is carrying out the additional drilling suggested at their cost.

 

The hydro-electric5 plant is to contain two vertical shaft turbo generator sets with a rated capa­city of 20 MW each and designed for a nominal discharge of 1,000 cusecs and an operating head of 268 feet. The maximum head would be 300 feet and the minimum 230 feet. At the downstream tunnel portal there would be a steel penstock, 13 feet in diameter at the beginning and bifurcates into 219’ diameter pipes and about 1,300 feet in length, which would enter a manifold from which two out­lets would convey the water to the turbine units with a third outlet to serve as a by-pass discharging directly into the tailrace which joins the Dhun Oya.

 

The Polgolla power plant would increase the firm power capacity of the system by about 20 MW and would contribute 180 million kWh of energy annually. In order to connect the power station to the existing 132 KV transmission network, the Ceylon Electricity Board would construct a short double-circuit 132 KY transmission line from the Switching Station located near Kandy.

Bowatenna Complex

 

The Bowatenna complex consists of a high diversion dam on the Amban Ganga at Bowatenna,. a 4-mile-long diversion tunnel on the left bank followed by about a mile long lined canal up to Dam­bulla Oya, a bifurcation structure at Dambulla Oya to release part of the flows to the Dambulla Oya which discharges into the Kalàwewa tank and the remaining part into a short earthen canal which will feed the Kandalama tank. (A reservoir with a net capacity of 7,500 ac. ft. will be constructed across Dambulla Oya under Stage 11).

 

The diversion dam would be a concrete structure. 741 feet long at the crest and 100 feet high with six radial gates and an earth embankment on the left bank having a spillway of length 222’ and a 16 feet wide roadway on the crest. The spillway would have a capacity of 125,000 cusecs which corres­ponds to a flood of 100 year frequency. The maximum operating pool level of the dam would be at elevation 820 feet and the minimum at 800 feet which would provide an active storage of 21,000 ac. ft. The geology of the site is favourable. Rock outcrops are exposed which are fractured and joined, consisting of gneisses and quartzite’s. Boreholes data along the dam axis shows some fracturing at depths, indicating the need for grouting.

The diversion tunnel was 22,468 feet long with an unlined horse-shoe section 13 feet in diameter capable of discharging 1,500 cusecs; about 30% of this tunnel will be protected by concrete lining and shotcreting. Six boreholes have been drilled along the 5 mile length of the tunnel. In the upper part of the tunnel, the rock formations consist of gneisses and quartzite which are fractured and joited. In the lower half of the tunnel the rock consists of calc gneisses and crystalline limestone. The ground­water table lies closer to the ground surface in the lower half of the tunnel alignment and may give rise to difficult problems of care of water during construction. Geologists from USOM, FAO and UNDP mentioned in Para 5 above, inspected the site and endorsed the feasibility of the tunnel. For supplying adequate information to contractors on the geology of the tunnel, additional drill holes were made along the axis.

 

The tunnel would lead to an open-cut with depth of cut varying from 65 to 15 feet in a length of 4,160 feet to Dambulu Oya. The canal would have a capacity of 1,500 cusecs and would be lined with concrete. At Dambulu Oya there would be a bifurcation structure for diverting 750 cusecs into the Dambulu7 Oya which feeds the Kalawewa tank while the remaining discharge of 250 cusecs would be conveyed through a short unlined canal, the Kandalama tank. Another bifurcation structure constructed at the end of this canal will divert 100 cusecs of the flow to 1-Iuruluwewa along a 16 mile canal which leads to Habaraua Oya for feeding Huruluwewa.

 

Sudu Ganga Training Works

 

Water released from the Polgolla tunnel and hydro-electric plant would be conveyed to Bowa­tenna through the natural channels of Dhun Oya, Sudu Ganga and Amban Ganga rivers. The addi­tional flow of up to 2,500 cusecs in these channels would affect their natural regime, particularly in the Dhun Oya and the upper reaches of the Sudu Ganga, where the existing capacity of the channels is less than 2,500 cusecs. Channel improvements and training works would be required to prevent erosion and damage to existing improvements. Inspection of the channels has also indicated that parts of the cultivated land along the banks of the Sudu Ganga, which would be subjected to flooding, may have to be acquired and 3 road bridges, on the Sudu Ganga would have to be remodelled to im­prove their Waterways. Some drop structures may have to be constructed to stabilize the channel.

 

Elahera-Minneri-Kantalai-Yoda Ela Canal

 

The Elahera-Minneri-Kantalai-Yoda Ela canal (referred to as the Elahera canal) is an old canal which has been restored and remodelled several times in the past two decades. It takes -off from the Elahera weir on the Amban Ganga and runs along a contour to the Minneriya tank with a by-pass feeder to the Giritale tank. It takes off again from the Minneriya tank, passes above the Kaudulla tank, augmenting the supplies to the latter through a special feeder and then spills into the Yoda Ela canal which discharges into the existing Kantalai tank. The total length of the canal from the Elahera weir to Kantalai tank is about 38 miles consisting of 22 miles from Elahera to Minneriya and 16 miles from Minneriya to Kantalai. Its present capacity is 1,000 cusecs in the’ first 4.9 miles, 1,250 cusecs from 4.9 to 6.3 miles and 1,500 cusecs ifl the remaining 15.7 miles to the Minneriya tank. From the Minneriya tank, the canal has a single bank on the right side and intercepts all the drainage from the left bank. Here it is in effect, a catch-water drain with large pools at places where the natural streams enter the canal. In view of its high right bank, it can carry over 2,500 cusecs of peak floods.

 

The entire canal from Elahera weir to Kantalai is poorly maintained. Below Minneriya tank, there is a heavy growth of weeds and bushes which restrict the waterway and cause heavy water losses.

 

In order to meet the full irrigation requirements of areas Dl and G, and also to fill the tanks in time for regulation and storage, the capacity of the Elahera canal would be increased to 1,600 cusecs up to the Minneriya tank. Beyond this point, no increase in the theoretical capacity is required, but considerable work has to be done to restore the waterway by clearing the weeds and bushes and widening the restricted sections. After the canal is fully remodelled, it would require heavy annual maintenance to maintain its capacity as the numerous natural streams entering the canal throughout its length would cause silting, encourage weed growth and create large standing pools. The alternative is to construct a regular canal with two banks, crossing all the natural drainage lines by siphons underneath the canal. This would require 146 drainage siphons to cross the 146 natural streams draining a catchment’s of 40 square miles on’ the left bank from Elahera to Minneriya and another 65 drainage siphons to cross the 65 natural streams draining a catchment’s area of 17 square miles on the left bank from Minneriya to Kantalai. The main advantages of this alternative would be the reduction of water losses and annual maintenance costs. However, the main disadvantages are the heavy capital cost of construction, the hazards of damage to the numerous cross drainage works during heavy rains, which would increase the annual maintenance cost and might also make the canal inoperative at times and, above all, the waste of an important source of water from the left bank catchments of the canal varying from 60,000 to 20,000 ac. ft. annually, which can be regulated in the tanks and utilized for irrigation.

 

The Elahera weir would be remodelled to raise its pond level by an additional 2 feet and a new head regulator would be constructed on the left bank, adjacent to the existing regulator, with a capacity of 700 cusecs to provide additional supplies to the Elahera canal. The first 1,000 feet of Elahera canal runs through a deep cut in rock and is lined with concrete.  It would be widened and re-modelled to increase its capacity to 1,500 cusecs.

 

investigations   Areas H and IH

 

Area H is estimated to contain 42,000 ac. of already irrigated land including Huruluwewa irriga­tion area and 71,000 ac. of new land, mainly under forest which is suitable for and capable of being• irrigated. Area in is estimated to contain 10,000 ac. of irrigated land; no new land is available. Additional irrigation, drainage and agricultural investigations are required in these areas before they can be appraised for further development. These investigations and studies would involve, but not be limited to, the following

 

(a)   Review of existing data and reports;

 

(b)   Aerial photography at. a scale of 1 :10,000 to enable production of rectified prints and mosaics;

 

             (c)    Review the existing contour mapping;

                
            
(d)    Land classification of areas at a scale of about 1: 10,000;

 

(e)   Water supply, water management and use studies, including seepage and evaporation losses and use of measuring devices;

 

(f)    Land development and on-farm development costs for existing and new land based on typical farm layouts from sample plots on representative areas covering 10% of the total irrigable area;

 

(g)   Agronomic and farm management studies to establish optimum cropping patterns with and without livestock;

 

             (h)    Socio-agro-economic studies of settlement patterns and suitable farm sizes;


              (i)    Establish an overall irrigation and drainage plan including flood control;


              (j)    Establish costs of recommended layouts;


             (k)    Study farm-to-market road requirements;

 

(I)    Review and advice on expanded agricultural extension service requirements and sitting and layout of demonstration farms;

 

              (m)  Determine project agricultural benefits using internal rate of return;

 

             (n)    Prepare interim and final feasibility reports; and                                               .

 

  (o)   Recommend type or organization suitable for execution and operation of Stage II.

 

 

On-Farm Development

 

If 7,000 ac. of sugarcane in area Dl are to benefit fully from the increased water supply that should be available by end of 1975, the irrigation and drainage systems will require levelling and sub-soiling. Equipment has been provided in the project to enable this work to be completed by the end of 1975.

 

It would be necessary for on-farm development work to be carried out immediately on 220 ac. prior to the arrival of equipment being provided under the project. This work would be done by equipment already in the country, to enable information to be obtained on the yield of sugarcane per acre, when water is no longer the constraint. This, in turn, wilt require the sugar cane estate to have a first call on the available water in the Kantalai tank for irrigating adequately 200 ac. of sugarcane throughout the year. This involves making available sufficient water to permit a minimum application of 2 in. of water to the root zone every 10 - 14 days.

 

Improvements to existing Irrigation Schemes

 

Nearly 126,585 acres of land in the existing irrigation schemes in systems Dl, 02, G, 1-I, ti-I and under Huruluwewa will receive sufficient irrigation water for two crops. These areas are presently being cultivated satisfactorily only during the Maha season. Special Projects are proposed to be set up in these areas in order to co-ordinate and improve the services available for farmers. Supply of inputs, extension services, marketing and credit facilities, and education for farmers on better water management, irrigation and farming practices will be done using these special projects in order to improve the efficiency of farming and the productivity in the area. Irrigation and drainage systems in these schemes will need improvements in order to facilitate the discharge of increased irrigation water supply. Necessary improvements mainly to the canals, structures and other waterways will be carried out to improve the efficiency of the irrigation and drainage network.

 

Kalawewa Head Works — Improvements

 

The active storage capacity of the Kalawewa Tank will be increased by 20,000 ac. ft. This will improve the regulation of irrigation supply to areas H and IH (under Kala Oya and Anuradhapura city tanks). For this purpose Kalawewa-Balaluwewa bund. will be raised by 4 feet. Main spill of Kalawewa will be raised and a radial gate installed. R. B. sluice will be reconstructed for a larger capacity for discharge and a new L. B. sluice will be constructed.

 

Bowatenna Power House

 

It has been proposed to harness the potential hydropower of the water flowing down the Bowa­tenna Dam. A hydro-electric power plant with an installed capacity of 40MW and an average annual power generation of 160 million kWh of energy will be constructed on the downstream of the dam. A short tunnel will be excavated through the left abutment of the dam which will be connected to a steel penstock for conveying water to the Power House. The water, after generating. hydropower will flow to Amban Ganga for irrigation systems D and G.