| Home

The
water resources of the Mahaweli Ganga Basin and its utilization
for agricultural and power development, as well as for other uses
had been studied over a period of four years and a Master Plan was
prepared accordingly. The Master Plan provided for a step wise implementation
of the Mahaweli Ganga development consisting of 15 multipurpose
projects;
04 trans-basin diversion canals; and several power stations, having
a total installed capacity of 960 MW over a period of 30 years.
The
first project, Polgolla Diversion Complex consisting of a diversion
dam built across the Mahaweli Ganga at Polgolla for diverting the
waters of the river to the Dry Zone through five miles long an under-ground
tunnel connecting Mahaweli to the Sudu Ganga, and Hydro-electric
power station of 40 MW. An extent of approximately 140 hectares
(350 acres) of land had been acquired for this complex.
Historical Background
The Master Plan
A
UNDP/FAO team with Sri Lankan counterparts carried out a survey
of the Irrigation and Hydro-Power potential of the Mahaweli Ganga
and the adjoining river basins during the four year period 1965-1968
and formulated a Master Plan for the development of the available
resources. The Master Plan is described in the three volumes on
“Mahaweli Ganga Irrigation and Hydro-Power Survey” FAO,
Rome in 1969.
The
plan envisages the development under irrigation of 900,000 acres
of land and generation of 2,037 million kilowatt hours of hydro
electric energy from an installed capacity of 507 megawatts. The
capital cost estimated in 1968 was Rs. 5,583 million, excluding
cost of activities resulting directly from the project, but having
their own economic justification, estimated at Rs. 1,120 million.
In view of the large magnitude of the work and investment involved,
the Master Plan was divided into three phases for purposes of implementation.
Phase
I of the Master Plan for which feasibility studies have been prepared
by the UNDP/FAO team has been sub-divided into three projects. The
sub division of Phases II and III was left to a later stage when
execution of the projects is taken up for consideration. Each of
the projects in Phase I, and Phases II and III were individually
evaluated and found to be economically viable. Each project can
be constructed in a period of 4 to 6 years. The entire master Plan
was phased for stepwise implantation over a time period of 30 years.
Back
Implementation:
Execution of Project I of Phase I was commenced in 1970 and completed
in 1977. It comprises of a barrage across the Mahaweli Ganga at
Polgolla to divert a maximum of 2,000 cusecs through a 5 mile long
pressure tunnel to a power plant of 40 MW installed capacity situated
in the adjacent Amban Ganga basin. The tail race water flows down
a tributary of the Amban Ganga into a reservoir at Bowatenna formed
by a concrete dam across the river, which diverts part of the flows
into the adjacent Kala Oya basin, through a 4 Mile long tunnel and
a Tran basin canal into Kalawewa and Kandalama reservoirs. The rest
of the diverted water along with the natural flow of the Amban Ganga
is sent down the river to be diverted at the existing Elahera and
Angamedilla diversion weirs into existing conveyance canals. The
total extent of land benefited by Project I is 132,000 acres of
existing fields and 91,000 acres of new lands.
The
discharged of 1,300 cusecs is sent farther down the Amban Ganga
and diverted at the Elahera anicut through Elahera – Minneriya-
Kantalai-Yoda Ela canal to Minneriya, and from there to Kaudulla
and Kantalai tanks, which supply water to system D-1. The Mahaweli
System ‘G’ is irrigated directly from this canal.
The
remaining 700 cusecs is transferred through the Polgolla-Kala Oya
canal (P K) to Kalawewa and Kandalama tanks, from which 70 percent
of System ‘H’ is irrigated.
Back
The Main Physical Components of the Project
Polgolla
Head works
General
Description:
Dam type - Concrete Barrage
Dam Height - 14.6 m
Length - 144 m
Gross Storage - 4.1 mcm
Live Storage - 2.1 mcm
Back
|