| Home

The
Randenigala Project, the fourth major multi-purpose project and
the largest reservoir under the Accelerated Mahaweli Development
Programme. Randenigala project is located about 26 km. below the
Victoria Head works and 6 km. upstream of Minipe anicut from where
the main Right Bank and Left Bank canals will divert the Mahaweli
waters for irrigation. It is also the reservoir with the largest
storage capacity having gross storage of 860 million cubic metres
(697,000 acre ft.) at full supply level. The project is expected
to generate about 525 GWh of electrical energy which amounts to
20% of the island’s present demand. It will serve as the most
important base reservoir for water management in System ‘A’,
‘B’ and ‘C’.
Project Features
The
project chiefly consists of the construction of a 94 m.(308 ft)
high, 485 m.(1590 ft.) long Rock-fill dam across Mahaweli, created
a reservoir of 860 million cu.m. (697,000 ac.ft.). The Power House
on the Left bank immediately downstream of the dam has an installed
capacity of 126 MW. A steel lined tunnel 6.2 m. dieameter, 270 m.
long, convey water to the Power House to run the turbines. The triple
gated chute spillway is 48 M. wide, about 232m. long and is capable
of discharging the probable maximum flood of 8085 cumecs.
Finances
The
total cost of these Headworks is approximately Rs. 4898 million
of which Rs. 1207 million is the local component and Dautsche Marks
410 million is the foreign component in 1985. The Federal Republic
of Germany first granted a loan for a value of about DM 240 million
(Rs.2160 million) and has extended a loan to the value of DM 400
million on favourable terms for Randenigala Project. (Rs. 2,528,455
as at the balance sheet 2004) (Rs.’000)
Back
Consultancy services
The
consultants for the Project is Joint Venture Randenigala (JVR),
a firms, Salzgitter Consult GmbH, Agrar-Und Hydro-technik GmbH and
Electrowatt Engineering Services Ltd along with the Engineers of
the Central Engineering Consultancy Bureau. (CECB)
Construction work commenced in 1982. The reservoir was impounded
in March 1986, construction of the rockfill dam, spillway and power
station were completed in 1986, according to schedule. The two turbine
generator units were commissioned in August and September 1986.
Back
Scope
A
dam at Randenigala site with power station and other appurtenant
structures together with a lower dam at Rantembe (immediately below
the confluence of the Uma Oya with the Mahaweli ganga), and power
station.
Back
Historical
Background
The
Main Physical Components of the Project
The
average rainfall within the Randenigala Project area ………
mm.
The
Randenigala Project basic parameters :
Dam
type Rockfill with Claycore
Back
Recervoir
(As
at Projects & Programme 1988)
Catchment area - 2,330 Km 2
Gross storage capacity - 861 MCM
Live storage capacity - 558 MCM
Surface at retention level - 1350Ha
Main Dam
Dam
Length - 485 m
Dam Height - 94.0 m
Crest elevation - 239.0 m MSL
Crest width - 10 m
Maximum base width - 303 m
Spill way
Maximum
capacity - 8,100 m 3/ s
Number of gates - 3
Type of gates - Taintor
Hight of gate - 15.26 m
Width of gates - 16.70 m
Length of chute spillway - 232 m
Back
Tunnel
Bottom & Irrigation Outlet
Length
- 5646 metres
Diameter of tunnel
Inside concrete lining - 6.2 metres
Depth of surge chamber - 116 meters
Generators & Turbines
Number
of turbine & Generator - 2
Type of turbines - Francis
Setting of turbines - 148.50 m MSL
Installed capacity - 2 x 63 MW
Annual estimated energy
Generation firm - 428 GWh (one million units)
Secondary - 100 GWh
(Sources
Projects and Programme 1988)
Back
|