1
BC |
First
Dam across Mahaweli River by King Kootakannatissa at “Meenwila”.
(Manampitiya) |
67
AD |
Construction
of Elahera Canal by King Vasba |
275-301
AD |
Elahera
Canal extended to Minneriya – Kaudulla by King Mahasena |
368
AD |
Angagamedilla
diversion dam across Ambangaga at Abgamedilla by King Upatissa
I |
571-604
BC |
First
Diversion of Mahaweli water through “Manimekhala”
now Minipe Left Bank Canal, the Trans-Basin Canal constructed
by King Agbo I |
853-857
AD |
Minipe
Ela extended by 47 miles by the King Sena II |
1153
AD |
Parakrama
Samudrha augmented from the canal called “Akasha Ganga”
which originated from Angamadilla by King Parakramabahu I |
1970
Feb 28 |
Mahaweli
Diversion Project inaugurated at Polgolla. |
1970
March 21 |
Mahaweli
Development Board Act No 14 of 1970 passed. |
1970
May 3 |
Mahaweli
Authority area gazetted |
1970
May 10 |
Construction
work of the Polgolla complex started |
1972
Jan |
Polgolla
complex commenced |
1973
March 30 |
Bowatenna
Complex inaugurated |
1973
May |
Kotmale
feasibility study commenced |
1974
Feb 15 |
Construction
work of Huruluwewa feeder canal commenced |
1976 |
Construction
work of Polgolla – Ukuwela Tunnel completed |
1976
Jan 08 |
The
Polgolla complex commissioned |
1976
March 18 |
Bowatenna
Tunnel opened |
1976
April 3 |
Kalawewa
– Balaluwewa sluice opened |
1976
May 23 |
First
release of Mahaweli water from the Kandalama Tank |
1976
Oct |
First
release of diverted Mahaweli water to the Huruluwewa reservoir |
1976
Nov 7 |
Mahaweli
water released from the Minneriya Tank to Kantalai |
1977
Sep 9 |
Agreement
signed with USAID for funding System H. |
1977
Oct 12 |
The
government decision to accelerate the Mahaweli Programme. |
1978
Jan 30 |
Construction
work of the Ulhitiya Project commenced |
1978
Aug 14 |
The
Maduru Oya Project commissioned |
1978
Sep 7 |
Ministry
of Mahaweli Development was established |
1978
Oct 15 |
Galnewa
New Town declared opened |
1978
Dec 21 |
EEC
Agreement to finance the System G Development signed. |
1979
Feb 4 |
Construction
work of Kotmale Project commenced |
1979
March |
Construction
work of Ulhitiya commenced |
1979
April |
Mahaweli
Authority of Sri Lanka established. |
1979
Aug 30 |
The
agreement with the USAID for re-forestation signed |
1979
Oct 20 |
Jaya
ganga sluice of Kalawewa opened |
1980
March 23 |
Construction
work of the Victoria Project commenced |
1980
April 10 |
Work
on the Victoria Dam & the Tunnel commenced |
1980
April 16 |
World
Bank – IDA Loan signed |
1980
June 04 |
Mahaweli
Settlement Division established |
1980
June |
690
settled in System C |
1980
June 14 |
Maduru
Oya Project commenced |
1980
Oct 31 |
ADB
Loan for Mahaweli Area Road Development signed |
1980
Nov 10 |
TAMS
Report (Mahaweli Environmental Study) completed |
1980
Jan 23 |
EEC
Agreement for Development of Zone 2 signed |
1981
Apr 16 |
Uda
Walawe Project handed over to MASL |
1981
July 31 |
Galnewa
Central College started |
1981
Nov 11 |
Agreement
for Randenigala Construction signed |
1981
Dec |
Mahaweli
Economic Agency established |
1982
Nov 21 |
Work
on the Randenigala Project inaugurated |
1983
Apr 9 |
The
Ulhitiya Reservoir commissioned |
1983
Jul 2 |
The
sluice gate of the Maduruoya Reservoir opened |
1984
Apr 4 |
Waters
of the Mahaweli in the Victoria Reservoir impounded |
1984
Apr 21 |
The
Minipe Right Bank Canal commissioned |
1984
Aug 27 |
The
first charge of hydrel power from the Victoria reached the
National Grid |
1984
Nov 17 |
The
Kotmale Reservoir impounded |
1985
Apr 12 |
Victoria
Project commissioned |
1985
Aug 23 |
The
Kotmale Project commissioned |
1986
Mar 23 |
The
Randenigala Reservoir impounded |
1986
Mar 23 |
Work
on the Rantambe Project commenced |
1986
Apr 11 |
Giradurdkotte
New Town opened |
1988
Mar 28 |
System
“L” gazetted as a special Area under Mahaweli
Authority |
1988
Nov 11 |
Welikanda
New Town opened |
1990
Mar 10 |
Kotmale
New Town opened |
1990
May 28 |
The
Rantambe power complex commissioned |
1994
Jan |
Padalangala
– Suriyawea – Mirijjawila New Road in Walawe commenced
|
1994
July 4 |
Engineering
studies for Walawe Left Bank commenced |
1995
Aug 31 |
OECF
loan agreement for rehabilitation and provision irrigation
facilities in Walawe Left Bank signed |
1996 |
Negotiations
with Kuwait Fund assistance for Moragahakanda Project commenced |
1996
Feb 11 |
Padalangala
– Suriyawewa – Mirijjawila new road network in
Walawe opened |
1996
May 17 |
EEC
Grant for rehabilitation of Systems C & G signed |
1996
July 7 |
Netherlands
Grant for Mahaweli System “C” multifunctional
Households environmental Project signed. |
1996
July 31 |
OECF
Loan Agreement for provision of irrigation facilities to Walawe
Left Bank extension area and rehabilitation work of the Walawe
reservoir signed |
1997
Feb |
Initial
work on rehabilitation work in System H commenced |
1997
Aug 6 |
Huruluwewa
Feeder Canal gazetted as Special Area under the Mahaweli Authority. |
1997
Aug 18 |
OECF
Loan Agreement for Mahaweli System C Upgrading Project was
signed. |
1997
June |
A
separate Ministry of Mahaweli was once again established. |
1997
Dec |
Implementation
of World Bank and Government of Sri Lanka Project on restructing
of the Mahaweli Authority commenced |
1997
Dec 6 |
Walawe
Left Bank Development work inaugurated |
1998
Jan 2 |
System
B Model Zone Development inaugurated |
| 1998 Feb |
Mahaweli Restructuring & Rehabilitation Project
(MRRP)
Established |
| 1998 |
6,263 employees (57% of total staff) voluntarily retired
under the VESP |
| 1999 |
Mahaweli Consolidation Project (MCP) commenced |
| 1999 Jun 14 |
Mahaweli Livestock and Agro enterprises (Pvt) Ltd
Incorporated as a Subsidiary Company of MASL |
| 1999 July |
Natural Resources Management Services (Pvt.) Ltd. |
| 1999 |
Mahaweli Engineering Services (Pvt.) Ltd |
| 1999 |
Uda walawe Left bank phase II, commenced |
| 2000 |
Mahaweli Engineering and Construction Agency (MECA) closed
down |
| 2000 Jan |
Village Self Help Learning Initiative Project (VSHLI)
was initially implemented under MRRP |
| 2001 Jan 10 |
Mahaweli River Basin Management Division was established
Under MRRP |
| 2001 Apr 01 |
Feasibility study on Moragahakanda / Kaluganga Basin Development
Project by Lahmeyer International commenced |
| 2002 Mar 01 |
Kala Oya River Basin Office was initiated under River Basin
and Management Division |
| 2002 |
100 days programme implemented |
| |
Women’s Bank were formed |
| 2003 |
Udawalawe Left bank Phase I completed |
| 2003 |
Integrated Basin plan for Kala Oya was completed |
| |
Hurulu Wewa Feeder Canal Improvement project |
| |
System B Left Bank development project
2004 March Gazetted the System D area (Medirigiriya) |
| |
Mini Hydro-power project
Ridimaliyadda project
Riverine Bamboo Project commenced
Pavitra Ganga programme activities commenced |
| 2004 June |
MRRP close down |
| 2004 Oct 31 |
A separate RPM Office was established to implement and develop
Medirigiriya Project in System ‘D’ |
| 2004 Nov 21 |
Water released from Walawe Left bank at auspicious time |
| 2005 May |
Mahaweli student hostel opened |
| 2005 Oct 26 |
Polonnaruwa – Manmpitiya Sama Palama (bridge) commenced
With Japanese aids |
| 2005 Nov 05 |
Dambulla- Bakamuna – Kalagahawela Road opened to the
Public |
| 2007 Jan 25 |
Moragahakanda Project Inaugural Ceremony |
| 2008 Aug 14 |
Dam Safety & Water Resources Planning Project (DSWRPP)
Launching ceremony at Parakarama Samudra |