| System
B Left Bank comprises 26,680 ha. of gross irrigable land of which
17,415 ha. of net area have been already opened up for agriculture.
16,836 farmer families and 5,090 non farmer families totaling to
21,926 families have been settled. Total estimated cost of the project
is Rs. 10,168 Mn. Expenditure up to September 2003 is. Rs.9,118
Mn. The project was financed by the Saudi Fund for Development,
European Union, USAID, OPEC and Government of Australia
Work items funded
by the SFD includes (a) Improvement of the 1 km of branch canal,
construction of about 115 km of Distributory canals, 265 km of field
canals, about 235 km of main, secondary and field drains and about
25 minor tanks in the project area. (b) jungle Clearing and Rough
leveling for Zones 2,3 & 4. (c) Construction schools, dormitories
& teacher's quarters and the provision of furniture for schools,
construction of social, administration & service building, utilities
& hamlet electrification in Zone 3 & 4. (d) Construction
of 4 km of MARD roads (link roads) about 144 km of Market Roads,
about 266 Km. of village roads and access roads in Zone 2, 3 &4
and bitumen surfacing of 154 km. of market roads in the project
area and (f) Provision of farm machinery, equipment, vehicles &
spare parts & agricultural implements & building materials
for farmers. Total loan amount was Saudi Riyals 85 m. (Rs. 607.325
m) (Saudi Riyal 1 = Rs.7.145 as at 30th May, 1984).
Development
works in Zone 1 , Zone 2 and Zone 5 have been completed while 78%
work in Zone 3 and 57% work in Zone 4A have also been completed.
Overall progress of project parts financed by SFD was 93% as at
end December 2003.
Budget allocation
for the year 2004 is Rs. 82.5 million. Targets for the year include
completion of balance work of water supply schemes, provision
|
|
|