| |
|
The
water resources of the Mahaweli Ganga Basin and its utilization
for agricultural and power development, as well as for other
uses had been studied over a period of four years and a Master
Plan was prepared accordingly. The Master Plan provided for
a step wise implementation of the Mahaweli Ganga development
consisting of 15 multipurpose projects.
04 trans-basin diversion canals; and several power stations,
having a total installed capacity of 960 MW over a period
of 30 years.
The first project, Polgolla Diversion Complex consisting of
a diversion dam built across the Mahaweli Ganga at Polgolla
for diverting the waters of the river to the Dry Zone through
five miles long an under-ground tunnel connecting Mahaweli
to the Sudu Ganga, and Hydro-electric power station of 40
MW. An extent of approximately 140 hectares (350 acres) of
land had been acquired for this complex.
Historical Background
The Master Plan
A UNDP/FAO team with Sri Lankan counterparts carried out a
survey of the Irrigation and Hydro-Power potential of the
Mahaweli Ganga and the adjoining river basins during the four
year period 1965-1968 and formulated a Master Plan for the
development of the available resources. The Master Plan is
described in the three volumes on “Mahaweli Ganga Irrigation
and Hydro-Power Survey” FAO, Rome in 1969.
The plan envisages the development under irrigation of 900,000
acres of land and generation of 2,037 million kilowatt hours
of hydro electric energy from an installed capacity of 507
megawatts. The capital cost estimated in 1968 was Rs. 5,583
million, excluding cost of activities resulting directly from
the project, but having their own economic justification,
estimated at Rs. 1,120 million. In view of the large magnitude
of the work and investment involved, the Master Plan was divided
into three phases for purposes of implementation.
Phase I of the Master Plan for which feasibility studies have
been prepared by the UNDP/FAO team has been sub-divided into
three projects. The sub division of Phases II and III was
left to a later stage when execution of the projects is taken
up for consideration. Each of the projects in Phase I, and
Phases II and III were individually evaluated and found to
be economically viable. Each project can be constructed in
a period of 4 to 6 years. The entire master Plan was phased
for stepwise implantation over a time period of 30 years.
Implementation
Execution of Project I of Phase I was commenced in 1970 and
completed in 1977. It comprises of a barrage across the Mahaweli
Ganga at Polgolla to divert a maximum of 2,000 cusecs through
a 5 mile long pressure tunnel to a power plant of 40 MW installed
capacity situated in the adjacent Amban Ganga basin. The tail
race water flows down a tributary of the Amban Ganga into
a reservoir at Bowatenna formed by a concrete dam across the
river, which diverts part of the flows into the adjacent Kala
Oya basin, through a 4 Mile long tunnel and a Tran basin canal
into Kalawewa and Kandalama reservoirs. The rest of the diverted
water along with the natural flow of the Amban Ganga is sent
down the river to be diverted at the existing Elahera and
Angamedilla diversion weirs into existing conveyance canals.
The total extent of land benefited by Project I is 132,000
acres of existing fields and 91,000 acres of new lands.
The discharged of 1,300 cusecs is sent farther down the Amban
Ganga and diverted at the Elahera anicut through Elahera –
Minneriya- Kantalai-Yoda Ela canal to Minneriya, and from
there to Kaudulla and Kantalai tanks, which supply water to
system D-1. The Mahaweli System ‘G’ is irrigated
directly from this canal.
The remaining 700 cusecs is transferred through the Polgolla-Kala
Oya canal (P K) to Kalawewa and Kandalama tanks, from which
70 percent of System ‘H’ is irrigated.
The Main Physical Components of the Project
Polgolla Head works
General Description:
Dam type - Concrete Barrage
Dam Height - 14.6 m
Length - 144 m
Gross Storage - 4.1 mcm
Live Storage - 2.1 mcm
|
|