| |
|
The
Randenigala Project, the fourth major multi-purpose project
and the largest reservoir under the Accelerated Mahaweli Development
Programme. Randenigala project is located about 26 km. below
the Victoria Head works and 6 km. upstream of Minipe anicut
from where the main Right Bank and Left Bank canals will divert
the Mahaweli waters for irrigation. It is also the reservoir
with the largest storage capacity having gross storage of
860 million cubic metres (697,000 acre ft.) at full supply
level. The project is expected to generate about 525 GWh of
electrical energy which amounts to 20% of the island’s
present demand. It will serve as the most important base reservoir
for water management in System ‘A’, ‘B’
and ‘C’.
Project
Features
The project chiefly consists of the construction of a 94 m.(308
ft) high, 485 m.(1590 ft.) long Rock-fill dam across Mahaweli,
created a reservoir of 860 million cu.m. (697,000 ac.ft.).
The Power House on the Left bank immediately downstream of
the dam has an installed capacity of 126 MW. A steel lined
tunnel 6.2 m. dieameter, 270 m. long, convey water to the
Power House to run the turbines. The triple gated chute spillway
is 48 M. wide, about 232m. long and is capable of discharging
the probable maximum flood of 8085 cumecs.
Finances
The total cost of these Headworks is approximately Rs. 4898
million of which Rs. 1207 million is the local component and
Dautsche Marks 410 million is the foreign component in 1985.
The Federal Republic of Germany first granted a loan for a
value of about DM 240 million (Rs.2160 million) and has extended
a loan to the value of DM 400 million on favourable terms
for Randenigala Project. (Rs. 2,528,455 as at the balance
sheet 2004) (Rs.’000)
Consultancy services
The consultants for the Project is Joint Venture Randenigala
(JVR), a firms, Salzgitter Consult GmbH, Agrar-Und Hydro-technik
GmbH and Electrowatt Engineering Services Ltd along with the
Engineers of the Central Engineering Consultancy Bureau. (CECB)
Construction work commenced in 1982. The reservoir was impounded
in March 1986, construction of the rockfill dam, spillway
and power station were completed in 1986, according to schedule.
The two turbine generator units were commissioned in August
and September 1986.
Scope
A dam at Randenigala site with power station and other appurtenant
structures together with a lower dam at Rantembe (immediately
below the confluence of the Uma Oya with the Mahaweli Ganga),
and power station.
Historical Background
The Main Physical Components of the Project
The average rainfall within the Randenigala Project area ………
mm.
The Randenigala Project basic parameters :
Dam type Rockfill with Claycore
Reservoir
(As
at Projects & Programme 1988)
Catchment
area - 2,330 Km 2
Gross storage capacity - 861 MCM
Live storage capacity - 558 MCM
Surface at retention level - 1350Ha
|
Turbines
Number
of turbine & Generator - 2
Type of turbines - Francis
Setting of turbines - 148.50 m MSL
Installed capacity - 2 x 63 MW
Annual estimated energy
Generation firm - 428 GWh (one million units)
Secondary - 100 GWh
(Sources Projects and Programme 1988)
|
|
Main
Dam :Double Curvation Arch Dam
Dam
Length - 485 m
Dam Height - 94.0 m
Crest elevation - 239.0 m MSL
Crest width - 10 m
Maximum base width - 303 m
Spill way
Maximum capacity - 8,100 m 3/ s
Number of gates - 3
Type of gates - Taintor
Hight of gate - 15.26 m
Width of gates - 16.70 m
Length of chute spillway - 232 m
|
Tunnel
Tunnel
Bottom & Irrigation Outlet
Length - 5646 metres
Diameter of tunnel
Inside concrete lining - 6.2 metres
Depth of surge chamber - 116 meters
|
|
|